SOS NERC PREP – RELIABILITY Latest Exam (QUESTIONS WITH VERIFIED ANSWERS) A+ GRADED

Instelling
SOS NERC PREP – RELIABILITY
Vak
SOS NERC PREP – RELIABILITY











Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
SOS NERC PREP – RELIABILITY
Vak
SOS NERC PREP – RELIABILITY

Documentinformatie

Geüpload op
23 oktober 2024
Aantal pagina's
88
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

SCORE MORE




SOS NERC PREP – RELIABILITY Latest Exam
(QUESTIONS WITH VERIFIED ANSWERS) A+
GRADED

The Reliability Coordinator just informed you of a slow time error correction which will begin at the top
of the next hour. Your EMS system will not let you change your scheduled frequency. Your Frequency
Bias Setting is -100 MW/.1Hz. What action should you take?



A) Increase Net Interchange Schedule by 20 MWs.



B) Inform the Reliability Coordinator that you cannot participate in the time error correction.



C) Decrease Net Interchange Schedule by 20 MWs.



D) Increase Net Interchange Schedule by 10 MWs.

A) Increase Net Interchange Schedule by 20 MWs.




A Balancing Authority has a sudden loss of a large block of load in its area. This loss will be seen
instantaneously in the change of which of the following values?



1. Actual Net Interchange

2. Scheduled Frequency

3. Scheduled Net Interchange

4. Area Control Error

,SCORE MORE


A) 4 only

B) 1 & 3

C) 1 & 4

D) 3 & 4

C) 1 & 4




Metered Data included in the calculation of ACE are: dynamic schedules, pseudo ties, actual frequency,
and all __________.



A) Tie lines readings

B) Generators output

C) Scheduled frequency indications

D) Transformer load

A) Tie lines readings




Balancing Authority A is currently reading a system frequency of 60.00 Hz. Its Net Actual Interchange is
+100 MW and its Net Scheduled Interchange is +200 MW. If Balancing Authority A's frequency bias
setting is 100 MW/0.1 Hz, what is ACE?



A) -100

B) 0

C) 10

D) 100

A) -100

,SCORE MORE


A Balancing Authority has a Net Interchange Schedule of -250 MWs from 1200 to 1600 on a summer
day. The Net Interchange Actual for those same hours respectively were -230 MW, -275 MW, -250 MW
and -270 MW. What was the Balancing Authority's Inadvertent Interchange for the 4-hour period?



A) 6 MWs out

B) 25 MWs in

C) 25 MWs out

D) 6 MWs in

B) 25 MWs in




For the ACE equation to work properly, dynamic schedules, pseudo ties, frequency, and all
________________ must be metered.



A) Generation

B) Communications

C) Transformers

D) Tie lines

D) Tie lines




If the frequency bias setting is set to a less negative value than the frequency response of a Balancing
Authority and a frequency increase is caused by a sudden loss of load in an external balancing area,
what will be the result?



A) The ACE will be zero and will take no AGC action



B) The ACE will be a negative value and AGC will increase generation



C) The ACE will be a positive value and AGC will lower generation

, SCORE MORE




D)This will not affect the ACE

B) The ACE will be a negative value and AGC will increase generation




If the frequency bias setting is less negative than the frequency response of a Balancing Authority and a
frequency decline is caused by a sudden loss of generation in an external balancing area, what will be
the result?



A) The ACE will be a negative value and AGC will increase generation.



B) This will not affect the ACE.



C) The ACE will be a positive value and AGC will lower generation.



D) The ACE will be zero and will take no AGC action.

C) The ACE will be a positive value and AGC will lower generation.




It is the responsibility of which entity/entities to develop, maintain, and implement load shedding plans?



A) Transmission Operators and Balancing Authorities



B) Reliability Coordinator



C) Load Serving Entities



D) Balancing Authority

A) Transmission Operators and Balancing Authorities

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
TOPMARKSOLUTIONS Boston College
Bekijk profiel
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
155
Lid sinds
3 jaar
Aantal volgers
97
Documenten
1031
Laatst verkocht
1 week geleden
TOPMARKSOLUTIONS

I TOPMARKSOLUTIONS have done research wide and far to make sure that I have provided you with the best and legitimate study resources. This resources include ;FINAL EXAMS, MIDTERM EXAMS, QUIZS, WEEKLY BASED KNOWLEDGE CHECKS, TESTBANKS ,ASSIGNMENTS & HOMEWORKS. I deal majorly in NURSING, MATHEMATICS ,BIOS & BUSSINESS

4.7

261 beoordelingen

5
199
4
50
3
5
2
1
1
6

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen