SAFE ADV SCRUM MASTER EXAM WITH GUARANTEED ACCURATE ANSWERS
What might be included in a team's improvement backlog?
Training needed by the team for future Iterations
Re-architecture of the Solution
Product Features
A running list of current software defects - Accurate Answers✔✔✔
Training needed by the team for future Iterations
What is one way a Scrum Master can gain the confidence of a
stakeholder?
Make the process visible
Invite the stakeholder to the Iteration retrospective
Make sure the results of the retrospectives are made public
,Establish a daily sync meeting with the stakeholder - Accurate
Answers✔✔✔ Make the process visible
What is one problem with phase-gate Milestones?
They assume a point Solution exists and can be built right the first time
They require the Product Owner to act as gatekeeper or guardian of the
process
They account for variability inherent in the process
They force design decisions too late in the process - Accurate
Answers✔✔✔ They assume a point Solution exists and can be built
right the first time
What is one requirement for achieving Continuous Deployment?
Decouple deployment from release
Automate all unit-tests
Couple development cadence and deployment cadence
Create all Features using behavior-driven development - Accurate
Answers✔✔✔ Decouple deployment from release
How is team performance calculated in SAFe?
The ratio of business value achieved to business value planned for the PI
The ratio of tasks planned to tasks completed
The ratio of Story points completed to Story points planned in the PI
, Team member utilization as a percentage of total capacity - Accurate
Answers✔✔✔ The ratio of business value achieved to business value
planned for the PI
How can a Scrum Master help the team remain focused on achieving
their Iteration goals?
By eliminating impediments
By supporting the rules of the team process
By leading a team's efforts in relentless improvements
By exhibiting Lean-Agile Leadership - Accurate Answers✔✔✔ By
eliminating impediments
How are the program risks, that have been identified during PI Planning,
categorized?
Resolved, Owned, Accepted, Mitigated
Resolved, Owned, Acknowledged, Managed
Removed, Owned, Accepted, Managed
Removed, Owned, Acknowledged, Mitigated - Accurate Answers✔✔✔
Resolved, Owned, Accepted, Mitigated
What is the purpose of the scrum of scrums meeting during PI Planning?
To create the program board
To track planning progress across the ART
To discuss scope changes