Storm Water Exam Questions And Answers 100% CorrectStorm Water Exam Questions And Answers 100% CorrectStorm Water Exam Questions And Answers 100% CorrectStorm Water Exam Questions And Answers 100% CorrectStorm Water Exam Questions And Answers 100% CorrectStorm Water Exam Questions And Answers 100% ...
Storm Water Exam Questions And
Answers 100% Correct
under natural conditions the majority of rain water that falls to the ground
___________________ - ANSWER-infiltrates the ground or evaporates
the introduction of pollutants to storm water most commonly occurs when industrial
facilities allow operating procedures and industrial materials to __________________ -
ANSWER-become exposed to storm water
the best way to prevent contamination of storm water is ___________________ -
ANSWER-through pollution prevention
The highest percentage of pollutants in storm water runoff occurs in the first few
minutes that storm water runs off. This is called the _________________. - ANSWER-
first flush
Organic enrichment of storm water runoff from sources such as food processing, airport
deicing, antifreezes, and sewage create addition oxygen demand in lakes and streams.
Much of the demand is due to bacteria feeding on these materials. The increased
oxygen demand can lead to ____________________________________, which is a
common cause of fish kills. - ANSWER-oxygen depletion
The addition of nitrogen and phosphorus to storm water runoff can result in algal blooms
and excessive growth of aquatic plants in fresh water systems such as lakes and
streams. In fresh water systems _____________________ is the main cause of
excessive plant and algal growth. - ANSWER-phosphorus
,Sediment is one of the most widespread pollutants in surface water. Many
___________________________ attach to finer sediment particles. Sediment can also
be destructive to aquatic systems by covering and damaging habitat. - ANSWER-
pollutants
Michigan law requires that anyone who discharges liquid wastes to surface waters of
the state must have their pollution control measures under the supervision of a
__________________________________________. - ANSWER-certified operator
If there is a construction activity at an industrial facility that disturbs one or more acres
of land or the soil disturbance is within 500 feet of a water body, the owner of the
property will need to apply for a
_________________________________________________________________
permit. In addition if the soil disturbance will become five or more acres in size the
property owner will need to submit the Notice of Coverage application to the EGLE,
Water Resources Division. - ANSWER-soil erosion and sedimentation control
A sewer system in which the storm water is kept separate from sanitary sewage and
discharges directly into a surface water body is called a ________
_____________________________________________. - ANSWER-separate storm
sewer system
A sewer system in which the sanitary sewage and the storm water are combined and
are directed to a wastewater treatment plant is called a
___________________________________________________. - ANSWER-combined
sewer system
For industrial facilities that are regulated by the federal regulations and there is a point
source discharge, but there is no exposure of industrial materials, the no exposure
certification must be submitted every __________ in MiWaters. - ANSWER-5 years
, __________________ permits are not site specific and contain the minimum
requirements for protecting water quality. - ANSWER-general
The ______________________________________ is a document that authorizes the
discharge of storm water under a general storm water permit. - ANSWER-certificate of
coverage
__________________ permits are site specific and contain requirements such as
regular sampling, monitoring, end of pipe treatment or effluent limits. - ANSWER-
individual
There are two types of industrial storm water general permits in Michigan they are
Storm Water from Industrial Activity and Storm Water with _________
______________________________________. - ANSWER-required monitoring or
special use areas
A facility that has the industrial storm water general permit with required monitoring or
special use areas is required to conduct a
_______________________________________________________________
_______________________________________. - ANSWER-short term storm water
characterization study
An annual fee will be assessed to all facilities that have permitted storm water
discharges. All facilities that have authorization to discharge storm water on
_________________________ will be responsible for the annual fee. - ANSWER-
January 1
Industrial facilities are identified in the federal storm water regulations by
_________________________________________ and narrative description. -
ANSWER-standard industrial classification (SIC) code
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller NursingTutor1. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $14.99. You're not tied to anything after your purchase.