100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
NERC Post Assessment Actual Final Exam Questions with all Questions Accurately Answered 2023/2024 $11.99   Add to cart

Exam (elaborations)

NERC Post Assessment Actual Final Exam Questions with all Questions Accurately Answered 2023/2024

 11 views  0 purchase
  • Course
  • NERC
  • Institution
  • NERC

NERC Post Assessment Actual Final Exam Questions with all Questions Accurately Answered 2023/2024 Auto-load - correct answer a feature on some generators that automatically moves the generator to a target load (mw) level. Automatic generation control (agc) - correct answer equipment that ...

[Show more]

Preview 4 out of 116  pages

  • October 24, 2024
  • 116
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • NERC
  • NERC
avatar-seller
KieranKent55
NERC Post Assessment Actual Final Exam
Questions with all Questions Accurately
Answered 2023/2024

Auto-load - correct answer a feature on some generators that
automatically moves the generator to a target load (mw) level.


Automatic generation control (agc) - correct answer
equipment that automatically adjusts generation in a balancing
authority area from a central location to maintain the balancing
authority's interchange schedule plus frequency bias. Agc may
also accommodate automatic inadvertent payback and time error
correction.


Automatic operations systems - correct answer special
protection systems, remedial action schemes, or other operating
systems installed on the electric systems that require no
intervention on the part of system operators.


Auto-transformer - correct answer a power transformer with a
single coil. The entire coil acts as the primary winding while a
portion of the same coil acts as the secondary winding.


Auxiliary relay - correct answer a relay whose function is to
supplement the actions of other types of relays. For example, a
lockout relay is an auxiliary relay with numerous contacts that
each can perform an action. The ieee has numbers assigned to
two types of auxiliary relays; 86 (lock-out) and 94 (tripping).

,Availability - correct answer a measure of time a generating
unit, transmission line, or other facility is capable of providing
service, whether or not it actually is in service. Typically, this
measure is expressed as a percent available for the period under
consideration.


Available flowgate capability (afc) - correct answer the
available capacity in mw or mva on a flowgate, which a
transmission service provider has determined, is available for
sale. The available capacity determined will be dependent on the
generation, loads and transmission configuration assumed for the
time period studied and therefore is referred to as a capability.
The afc will account for all thermal, voltage and stability limits
under both pre and post contingency conditions, along with any
trm or cbm. There is no one set of source and sink points
associated with an afc. The afc can be used to determine the
amount of mw that can be transferred between a specific set of
source and sink points with respect to the flowgate, by dividing
the afc by its corresponding ptdf.


Available transfer capability (atc) - correct answer a measure
of the transfer capability remaining in the physical transmission
network for further commercial activity over and above already
committed uses. It is defined as total transfer capability less
existing transmission commitments (including retail customer
service), less a capacity benefit margin, less a transmission
reliability margin.


Avoided cost - correct answer the cost the utility would incur
but for the existence of an independent generator or other
energy service option. Avoided cost rates have been used as the
power purchase price utilities offer independent suppliers.

,Back emf (conductors back emf) - correct answer when ac
current flows through a conductor an alternating magnetic field
is created. This alternating magnetic field induces a voltage in
the conductor. The induced voltage is called the conductor's back
emf.


Back-to-back hvdc - correct answer an hvdc system in which
ac is converted to dc and then immediately back to ac. The hvdc
transmission path is very short, normally consisting of a short
section of buswork.


Backup power - correct answer power provided by contract to
a customer when that customer's normal source of power is not
available.


Balancing authority - correct answer the responsible entity
that integrates resource plans ahead of time, maintains
loadinterchange-generation balance within a balancing authority
area, and supports interconnection frequency in real time.


Balancing authority area - correct answer the collection of
generation, transmission, and loads within the metered
boundaries of the balancing authority. The balancing authority
maintains load-resource balance within this area


Bandwidth - correct answer the acceptable range of a
quantity. For example, if it is desired to hold the voltage at a 345
kv bus between 355 and 360 kv then the bandwidth is 355 - 360
kv or 5 kv.

, Banking - correct answer energy delivered or received by a
utility with the intent that it will be returned in kind (as energy)
in the future.


Base load - correct answer the minimum amount of electric
power delivered or required over a given period at a constant
rate.


Base load capacity - correct answer capacity used to serve an
essentially constant level of customer demand. Base load
generating units typically operate whenever they are available,
and they generally have a capacity factor that is above 60%.


Base load generating units - correct answer generators that
normally run continuously to serve a balancing authority's load.


Bilateral payback - correct answer inadvertent interchange
accumulations paid back via an interchange schedule with
another balancing authority.


Bipolar hvdc - correct answer an hvdc system that uses two
conductors. One conductor is energized with a positive voltage
and the other a negative voltage.


Black-start unit (bsu) - correct answer a generating unit that
has the ability to go from a shutdown condition to an operating
condition and start delivering power without assistance from the
power system the generator normally connects to.

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller KieranKent55. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $11.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

67866 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$11.99
  • (0)
  Add to cart