ASPE CPD STUDY QUESTIONS AH
(QUIZBANK) ANSWERED CORRECTLY TO
SCORE A+
Front Answer - Back
What is the specific weight of water? Answer - 62.4 lbs per cubic foot
What happens in a storm and sanitary system after it passes the water test?
Answer - A smoke pressure test is recommended with a smoke pressure of 1 in
wc to prove the system gas tight.
Is an air test acceptable for a storm and sanitary system? Answer - Yes, if a
water test is not possible, at a pressure of 5 psi, are tests are impractical and
costly
What are the testing procedures for the storm and sanitary system? Answer -
A water test upon completion of the rough piping and prior to concealment of
10 ft wc minimum (except the topmost 10 feet of pipe), not to exceed 100 ft
wc. If system is higher than 100 feet, test plugs must be installed to facilitate
testing, rarely are more than 7 stories tested at one time. A peppermint oil test
may also be done with 2 oz of peppermint oil and 10 qt boiling water, and
searching for peppermint smell at leaks, however it is difficult to pinpoint the
leak by this method
The maximum length from the vent connection to any future drain outlet is
required by code, why, how long is the distance (listed in the book), and
what’s the exception? Answer - To prevent a dead end where slime, sludge
,and fungi can grow, 2 feet, unless the piping must be extended to an accessible
location for a cleanout
A sanitary tee may be used in the vertical but what may not be used in the
vertical and why? Answer - A double sanitary tee because the possibility of
flow crossover and excessive pressures when one branch is discharging and the
other isn’t are possible
What are the slopes of pipe inside the building that correspond to 2 fps
velocity? Answer - 1/4 in per foot for 3 in and smaller 1/8 in per foot for larger
pipe all elbows, taps, tees etc are tapped at a pitch of 1/4” per foot
Where should cleanouts be provided? Answer - 1) Inside or outside the
building at the point of exit (use a wye branch) 2) at every change in direction
greater than 45 degrees 3) every 50 feet for piping 4” and less, and 100 ft for
larger piping 4) underground piping larger than 10 in should be provided with
manholes at every change in direction and every 150 feet 5) at the base of all
stacks 6) as required by code
What size cleanouts are provided in piping? Answer - Piping up to 4 inches, the
cleanout is the same size as the pipe. Piping greater than 4 inches, 4 inch
cleanouts are adequate.
What should be installed in the house drain if there is a danger of backflow of
sewage into the building? Whats the difference? Answer - A backwater valve
or a combination BWV with manually operated gate valve. The BWV does not
interfere with the airflow throughout the system, and the gate valve is
recommended where there is a history of backflow as a positive means of
protection.
Branch connections to the house drain should be made where and why?
Answer - At the upper portion of the pipe (above the 1/2 - 2/3 full mark)
,because: 1) there is a lower chance of stoppages in the branch 2) there is less
flow interference at the point of connection 3) When there is no flow in the
branch, the full area of the pipe is available to relieve pneumatic pressure
fluctuations in the house drain
How many fixture units are equivalent to 1 gpm continuous or semicontinuous
flow and what are examples of these types of flow? Answer - 2 FUs, sump
pumps, ejectors, air conditioning equipment, water cooled, equipment, etc
What minimum slopes are required for building drains and why? Answer - 3 in
pipe and smaller: 1/4 in/ft 4-6 in pipe: 1/8 in/ft 8 in pipe and larger: 1/16 in/ft
to maintain 2 fps scouring action if low flow fixtures are present, 1/4 in/ft for all
is a good idea
House drains are designed to flow how full? Answer - 1/2 full to 3/4 full max
under uniform flow conditions
What is a house (building) drain? Answer - The lowest piping of a gravity
drainage system that receives the discharge from soil, waste, and other
drainage pipes inside the building that extends a short distance from the
building and conveys the drainage to the building sewer
What is the measurement from horizontal that separates horizontal and
vertical drainage stacks? Answer - 45 degrees
Does an interior drainage stack that offsets 45 degrees or less from the vertical
require a change in size? Answer - No. Any more than a 45 degree offset
requires sizing the offset as a house drain.
What is a branch interval? Answer - A building story or a distance between two
branch connections greater than 8 feet apart.
, Describe the procedure for sizing interior drainage stacks. Answer - 1) First size
the horizontal branches connecting to the stack 2) Determine the minimum
size that will accept each branch at one branch interval 3) Total all fixture units
connected to the stack, and determine the size. The minimum size must be at
least equal to the largest diameter required at the base. You may reduce in size
at upper branch intervals, but never by more than 1/2 the largest size.
What is the total recommended maximum permissible flow in a stack? Answer
- 7/24 of the total cross sectional area of the stack.
Where should and shouldn’t you connect branch connections to stack
offsets? Answer - Not to the horizontal offset to the stack if at all possible,
unless its at least 10 pipe diameters downstream, and ideally 2 feet above the
offset or 2 feet below to avoid pressure fluctuations.
What can minimize hydraulic jump? Answer - Increasing the slope of the
horizontal drain. Connecting to a horizontal drain that is larger than the stack.
Any offset of the stack greater than what can cause hydraulic jump? Answer -
45 degrees
When does terminal velocity occur in a drainage stack? Answer - It is achieved
at approximately 10 - 15 fps and this velocity is achieved within 10 - 15 feet of
fall from the point of entry.
A drainage stack should never be designed for a capacity greater than what and
why? Answer - One-thrid full, because the pressure fluctuations in the system
could greatly exceed the maximum 1 in water column criterion and lose their
seal by siphonage blowout
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller EvaTee. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $28.99. You're not tied to anything after your purchase.