KENTUCKY BOILER EXAM NEWEST 2024-2025 ACTUAL
EXAM COMPLETE 270 QUESTIONS AND CORRECT
DETAILED ANSWERS (VERIFIED ANSWERS
A license is required
when a person/firm
- installsr
a boile
-repairs a
boiler
- installs an
unfired boiler
- repairs an
unfired boiler
,- all of the above -
ANSWER-All of the above
T/F: License Is issued to a person designated as a license holder, and remains with that person,
regardless of change of an employer - ANSWER-True
A contractor may apply for a re-reinstatement of a license after how many days from the day the
suspension? - ANSWER-90 days
T/F: All on-site workers are also be required to be a licensed. - ANSWER-False, installers do not
need a license
As a license holder, can you pull a permit and then sub out the installation work? - ANSWER-No,
you cannot sub out boiler installation work.
Permit is required for the installation of a:
- boiler pressure vessel or pressure pipe
- replacement of pressure piping
- water heaters less than 15 psi
,- All of the above - ANSWER-All of the above
In emergency repair, permit first authorized by the board inspector, or a special bore inspector
shall be filed within or completed by... - ANSWER-30 days
When should a license holder submit a permit request for installation of a board press reversal
or piping to the department for approval? - ANSWER-Prior to
installation
T/F: A license holder may place boiler pressure vessel or pressure piping into service prior to
contacting the inspector - ANSWER-False
The law that requires all pressure vessels and boilers to be inspected before activation -
ANSWER-KRS 236
The willful violation of any provision of the law referred to in KRS 236 or KAR 815 is punishable
by... - ANSWER-30 days in jail and maximum $500/day
NBIC - ANSWER-National Board of Inspections and Code
, If there is a discrepancy between KRS 236 and 815 KRS in the regulation versus the national
board inspection code, which code takes precedent? - ANSWER-
NBIC
What is the ASME? - ANSWER-American Society of Mechanical Engineers
The minimum clearance required for a bore or pressure vessel all the side all around it? -
ANSWER-2' on each side
Clearance required for a manway? - ANSWER-5' clearance
T/F: Compressed air piping is considered pressure pipe? - ANSWER-True
T/F: Ammonia piping may be painted prior to the inspection if the contractor has the material
test reports on file. - ANSWER-False - No piping should be painted
prior to an
inspection
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller nyagajoseph539. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $25.99. You're not tied to anything after your purchase.