Project Management Plan - answer-A team is developing the project charter and is determining the valuable inputs used for completing the project. The input(s) that the team should least likely consider when developing the project charter would be the:
Fast Tracking - answer-In order to complete ...
PMI Final Exam Review
Project Management Plan - answer-A team is developing the project charter and is determining
the valuable inputs used for completing the project. The input(s) that the team should least likely
consider when developing the project charter would be the:
Fast Tracking - answer-In order to complete the finished attic remodel project on time, Brian
decides to hang the ceiling fan while Petrina paints the walls. This is an example of schedule:
Project Constraints - answer-Tammy is a construction project manager. The stakeholders for
this neighborhood project require the neighborhood be built within city limits so the end users
will have city water. This requirement would be listed under what section in the project scope
statement?
Determine Budget - answer-The project manager would like to determine the aggregate
estimated costs from the individual work packages to create a detailed breakdown of projected
costs. In which process is the project manager most likely participating?
Project Funding Requirements - answer-Liz looks at the activity costs that must be incurred to
complete all project deliverables. Liz is determining the:
$1,500 - answer-Emily is adding a garden to her yard. She estimates the work to build a raised
garden will be $250 per day and will take six days to complete. What is the project's budget at
completion?
Corrective Action - answer-A project manager has discovered that a project is outside the
original scope. The project manager has requested a change to bring expected future
performance of the project work back in line with the project management plan. What type of
change implementation has the project manager requested?
Enterprise environment factors - answer-Jen is a construction project manager. Her current
project has been halted due to a shortage in the demand for housing. The housing shortage
impact on the success of the project can be referred to as:
The customer has to formally accept the final product. - answer-Which activity must happen
before a project can officially close?
Control Scope - answer-Felicia is an event project manager. She is meeting with her conference
stakeholders to ensure the scope of products delivered aligns with what was planned for in the
scope baseline of the project. Which process is Felicia conducting?
Reserve analysis estimating - answer-Maria determines the project duration by overestimating
what she calculates by 15%. Maria is using:
Creating the WBS - answer-During what process is work decomposition performed?
Project Charter - answer-Delores has just been assigned to be a project manager of a team,
and she would like to find out more about a project. She is unsure of who can authorize the
project. What document should Delores consult?
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller TOPDOCTOR. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $9.49. You're not tied to anything after your purchase.