Clinger-Cohen Act/Defense Procurement Reform Act 1996 - ANSWER
Allows all federal agencies to utilize Design-Build. Before that, no enabling
legislation existed allowing Design-Build. What Year?
Standard of Care - ANSWER The level of quality that any average Design
Professional would be able to perform given the circumstances.
Design Build - ANSWER Fastest Project Delivery method, fast-tracking
possible overlapping design with construction utilizing incremental packages.
Negotiated (Qualifications Based) - ANSWER Procurement Method -
Common for A/E
GMP (Guaranteed Maximum Price) - ANSWER Contract Format - Combines
Cost-Plus & Lump-Sum, contractor reimbursed for actual cost plus a fee only
up to a certain amount.
Unit Price - ANSWER Contract Format - cost per piece
Hammurabi - ANSWER Singular responsibility for both design & construction
was first made into a building code by ____
Bridging Documents - ANSWER Owner provided items such as 20% design
or more and provides prescriptive specs at RFP.
Design Build - ANSWER Single point of responsibility for both design &
construction is an attribute of what delivery method?
Substantiation - ANSWER The process of checking milestones along the way
for completeness.
, Prescriptive - ANSWER Owner requiring specific products or methods be
instituted by DB team in order to achieve desired performance.
False - ANSWER T/F Detailed estimating is the Building systems approach to
estimating
False - ANSWER T/F feasibility estimate is cost model and establishes budget
for project
True - ANSWER T/F key element of quality assurance is keeping
communication lines open between owner and DB
True - ANSWER T/F in Design/cost relationship of DB, the constructor
establishes design parameters for architect
False - ANSWER T/F trust is most important thing for DB
Schematic estimating - ANSWER DB estimating sequence where 15%-20% of
design is completed
Trend logs - ANSWER Provides baseline budgets and schedules and list
estimate trends
Coordinating owner design reviews and approvals - ANSWER What is NOT a
design managers role?
Design Build Team - ANSWER Who is responsible for ensuring quality
assurance?
Weighted criteria - ANSWER Awarded to proposer with highest combined
total points of technical and price proposals
Conceptual estimating - ANSWER Estimate provided with very little design
Trend estimating - ANSWER Maintains control of budget and design process
between major estimate phases
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller luzlinkuz. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $11.49. You're not tied to anything after your purchase.