HSI Final Test Questions with Correct Answers 100% Pass The initial response to a frequency deviation is due to which of the following 1. Load / frequency response 2. AGC 3. Governor action 4. Interchange schedules •3 and 4 •1 and 2 •2 and 3 •1 and 3 - ANSWER-•1 and 3 EMS and AGC have failed at 12:25 and generation must be controlled manually. The operator calculates ACE to be +25 MWs. Load is expected to increase 100 MWs, and imports will increase by 75 MWs at the top of the hour. What should the operator do? •Maintain current generation level Copyright © OLIVIAWEST2024/2025 ACADEMIC YEAR. ALL RIGHTS RESERVED Copyright ©Stuvia International BV Page 2/40 •Decrease generation by 25 MWs •Decrease generation by 50 MWs •Increase generation by 25 MW - ANSWER-•Decrease generation by 25 MWs How is the Frequency Response Measure (FRM) of a Balancing Authority determined? •lt is the average of the BA's frequency response for all the frequency deviations of the previous year •lt is the change in the BA's Net Interchange Actual for the largest frequency deviation during the previous year •lt is the previous year's Control Performance Standard 1 ( CPS1 ) score •It is the median of the BA's frequency response for the frequency deviation events identified by NERC for the previous year - ANSWER-•It is the median of the BA's frequency response for the frequency deviation events identified by NERC for the previous year Sufficient Operating Reserve is defined as the capacity required to meet what? •DOE specifications •CPS and DCS •CPS 1 & 2 only •Capacity Standard - ANSWER-•CPS and DCS Copyright © OLIVIAWEST2024/2025 ACADEMIC YEAR. ALL RIGHTS RESERVED Copyright ©Stuvia International BV Page 3/40 In your Interconnection , a generator tripped that was large enough to reduce the frequency from 60.00 Hz to 59.94 Hz . Your Balancing Authority's Frequency Bias is -200 MW / 0.1 Hz . How many MW would your system initially contribute to frequency support? •120 MW •80 MW •100 MW •200 MW - ANSWER-•120 MW Interconnection frequency is 59.80 Hz . Your ACE is a large negative value and your AGC is pulsing your units down . What should you do •Leave AGC in operation but investigate •Place AGC in constant frequency control •Place AGC in flat tie line control •Suspend AGC and investigate - ANSWER-•Suspend AGC and investigate When a Balancing Authority's ACE value is the same sign as the frequency deviation , which NERC control performance score is affected negatively •DCS Copyright © OLIVIAWEST2024/2025 ACADEMIC YEAR. ALL RIGHTS RESERVED Copyright ©Stuvia International BV Page 4/40 •CPS 1 •TEC •BAAL - ANSWER-•CPS 1 Correct Of the following , which control system would be affected by a difference in Net Actual Interchange and Net Scheduled Interchange •Reactive Control •Turbine Governor Control •Automatic Generation Control •Automatic Voltage Regulator - ANSWER-•Automatic Generation Control Balancing Authority A is currently reading a system frequency of 59.98 Hz . Its Net Actual Interchange is +100 MW and its Net Scheduled Interchange is +100 MW . If Balancing Aut

Meer zien Lees minder
Instelling
Prep Tests
Vak
Prep Tests

Voorbeeld van de inhoud

Copyright © OLIVIAWEST2024/2025 ACADEMIC YEAR. ALL RIGHTS RESERVED




HSI Final Test Questions with Correct

Answers 100% Pass


The initial response to a frequency deviation is due to which of the following


1. Load / frequency response


2. AGC


3. Governor action


4. Interchange schedules




•3 and 4


•1 and 2


•2 and 3


•1 and 3 - ANSWER✔✔-•1 and 3


EMS and AGC have failed at 12:25 and generation must be controlled manually. The operator calculates

ACE to be +25 MWs. Load is expected to increase 100 MWs, and imports will increase by 75 MWs at the

top of the hour. What should the operator do?




•Maintain current generation level



Copyright ©Stuvia International BV 2010-2024 Page 1/40

, Copyright © OLIVIAWEST2024/2025 ACADEMIC YEAR. ALL RIGHTS RESERVED


•Decrease generation by 25 MWs


•Decrease generation by 50 MWs


•Increase generation by 25 MW - ANSWER✔✔-•Decrease generation by 25 MWs


How is the Frequency Response Measure (FRM) of a Balancing Authority determined?




•lt is the average of the BA's frequency response for all the frequency deviations of the previous year


•lt is the change in the BA's Net Interchange Actual for the largest frequency deviation during the

previous year


•lt is the previous year's Control Performance Standard 1 ( CPS1 ) score


•It is the median of the BA's frequency response for the frequency deviation events identified by NERC

for the previous year - ANSWER✔✔-•It is the median of the BA's frequency response for the frequency

deviation events identified by NERC for the previous year


Sufficient Operating Reserve is defined as the capacity required to meet what?




•DOE specifications


•CPS and DCS


•CPS 1 & 2 only


•Capacity Standard - ANSWER✔✔-•CPS and DCS




Copyright ©Stuvia International BV 2010-2024 Page 2/40

, Copyright © OLIVIAWEST2024/2025 ACADEMIC YEAR. ALL RIGHTS RESERVED


In your Interconnection , a generator tripped that was large enough to reduce the frequency from 60.00

Hz to 59.94 Hz . Your Balancing Authority's Frequency Bias is -200 MW / 0.1 Hz . How many MW would

your system initially contribute to frequency support?




•120 MW


•80 MW


•100 MW


•200 MW - ANSWER✔✔-•120 MW


Interconnection frequency is 59.80 Hz . Your ACE is a large negative value and your AGC is pulsing your

units down . What should you do




•Leave AGC in operation but investigate


•Place AGC in constant frequency control


•Place AGC in flat tie line control


•Suspend AGC and investigate - ANSWER✔✔-•Suspend AGC and investigate


When a Balancing Authority's ACE value is the same sign as the frequency deviation , which NERC control

performance score is affected negatively




•DCS




Copyright ©Stuvia International BV 2010-2024 Page 3/40

, Copyright © OLIVIAWEST2024/2025 ACADEMIC YEAR. ALL RIGHTS RESERVED


•CPS 1


•TEC


•BAAL - ANSWER✔✔-•CPS 1


Correct Of the following , which control system would be affected by a difference in Net Actual

Interchange and Net Scheduled Interchange




•Reactive Control


•Turbine Governor Control


•Automatic Generation Control


•Automatic Voltage Regulator - ANSWER✔✔-•Automatic Generation Control


Balancing Authority A is currently reading a system frequency of 59.98 Hz . Its Net Actual Interchange is

+100 MW and its Net Scheduled Interchange is +100 MW . If Balancing Authority A's frequency bias

setting is 100 MW / 0.1 HZ , what is ACE




• -20


•20


•2


•0 - ANSWER✔✔-• -20




Copyright ©Stuvia International BV 2010-2024 Page 4/40

Geschreven voor

Instelling
Prep Tests
Vak
Prep Tests

Documentinformatie

Geüpload op
11 november 2024
Aantal pagina's
40
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
OliviaWest Teachme2-tutor
Bekijk profiel
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
111
Lid sinds
1 jaar
Aantal volgers
17
Documenten
8496
Laatst verkocht
1 maand geleden
Pure Orchid Haven.

All Documents,and package deals offered by seller Olivia West.

2.8

22 beoordelingen

5
6
4
2
3
4
2
1
1
9

Populaire documenten

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen