UL 1741 - ANSWER Standards for inverters, converters, controller and interconnections
UL 1703 - ANSWER Standard for safety, flite plate, Pv modules and panels
What PV panels are made from cylindrical silicon ingot - ANSWER monocrystalline
Residential Pv systems are limited to no more than 24 two-volt cells connected in series
- ANSWER 48V in total per NEC 690.71
Roof mounted systems are mounted on aluminum or stainless steel rail secured secured
into the roof trusses using - ANSWER Lag Bolts
Diagnosing a PV problem - ANSWER Stay safe, look at system first, turn things off with
disconnects, then take measurements
PV monitoring systems - ANSWER consists of a device that measures current and
voltage on ac output of the inveter
PV source circuits meets PV output circuits - ANSWER in the combiner box
The point on the IV curve where the MPPT is maximum - ANSWER is at the third point
Current is measured with - ANSWER multimeter with a clamp
ARC flashes inverters are equipped with - ANSWER arc fault detection
, NEC - ANSWER contains which wire to use
OSHA - ANSWER Federal agency that establishes and enforces standards of safety for
the workplace
a restaurant uses 2200WH, 48 V dc, 4.9 PSH, and a Battery efficiency of 90%, what is the
Ah capacity needed? - ANSWER 2200WH/48V = 45.83 AH 45.83AH/.90 = 50.92 50.92/4.9
= 10.39
A restaurant uses 2WH and has 10 kWh in storage what can they operation? - ANSWER
They can operate all operations for days. 10 kWh is a lot of capacity compared to your
usage of 2 wh. First convert 10 kWh to 10,000 Wh which is a lot compared to 2 wh. Refer
to section 7.4.0 of your NCCER book for more detail.
When you lock out a system you need to use - ANSWER engraving
What was a non producing financial incentive for installing pv - ANSWER rebates
PV system warranties are for - ANSWER 25 years
what amps would cause an installer if shocked not be able to let go - ANSWER over
10MA
Inverter warranties - ANSWER are 10 years
Amps are represented by - ANSWER A
What should be done to PV modules to not energize and cause shock to a worker
ANSWER they must be covered and the leads plugged together
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller Easton. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $13.99. You're not tied to anything after your purchase.