CM 4211 Final Exam Study Questions Solved 100%
Correct | Verified Solutions
T - ✔✔If the owner's field rep. is not authorized to issue change orders, a contractor who
performs such a change may not get paid for the change work
T - ✔✔A construction change is a change to the work ordered by the owner but which the
owner feels does not require a change order
T - ✔✔A constructive change requires prompt notice by the contractor to the owner to allow
the contractor to get paid for the change work
T - ✔✔The force account method of equitable adjustment of cost when a change in the work
occurs requires daily records be kept of the change work agreed to by the owner's
representative on a daily basis
T - ✔✔On change work, the contractor may be entitled to impact costs in addition to
proximate costs provided that the contractor can prove such impact costs
T - ✔✔Failure of the owner to promptly investigate a differing site condition is a breach of
contract by the owner
T - ✔✔Prompt notification by the contractor to the owner of a differing site condition may
be waived by the courts if it is determined that the lack of notice did not prejudice the rights of
the owner
T - ✔✔An exculpatory clause in the contract relieving the owner from payment for changes
almost never outweighs a differing site conditions clause
,T - ✔✔One of the stumbling blocks to recovery on a differing site conditions claim is the
keeping of adequate records to support the damage amount
T - ✔✔A differing site condition is one of the three main reasons for delays in construction
contracting
T - ✔✔A delay in the work may be caused by owner interference
T - ✔✔A compensable delay entitles the contractor to a cost and/or time adjustment
T - ✔✔A "take it or leave it" contract is a contract adhesion
T - ✔✔If work is delayed by the owner, but the contractor still completes the work within the
contract time limits, the contractor may be entitled to a cost adjustment
T - ✔✔The two main reason of giving notice to the owner of a delay is to start the delay time
period and to give the owner time the opportunity to do something about the delay, if possible
T - ✔✔Constructive notice is when the owner is charged with knowledge of a delay even
though the construction contractor does not give actual notice of the delay
T - ✔✔Liquidated damages are an agreed upon amount per day for each day that the
contract is finished after the adjusted completion date
T - ✔✔Liquidated damages are not a penalty
T - ✔✔Force majeure means a condition beyond the control of a party
, T - ✔✔To support a claim for a time extension, a construction contractor must support the
claim by showing the delay was beyond its control and that it consumed time affecting
completion of the project
T - ✔✔Acceleration is the completion of contract work at a more rapid pace than required by
the contract
T - ✔✔Constructive acceleration is the forced completion of contract work in a shorter
period than should have been allowed by the issuance of a properly supported contract time
extension
T - ✔✔The failure of the owner to timely grant a time extension may result in constructive
acceleration
T - ✔✔Course of dealing is determined by how the owner and the construction contractor
performed on prior contracts
T - ✔✔Customs and trade practices are not considered when determining the clarity of the
express contract terms
T - ✔✔Reading the contract "as a whole" means that an interpretation must be considered
in context
T - ✔✔To prove course of dealing necessarily requires parole evidence
T - ✔✔The doctrine of contra proferentem is only considered a last resort
T - ✔✔The doctrine of contra proferentem states the contract will be construed against the
drafter of the document when all other manifestations do not resolve the problem
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller Examsplug. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $13.49. You're not tied to anything after your purchase.