100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
WGU C176 EXAM PREPARATION TEST BANK 2025 CONTAINS WGU C176 QUIZZES, WGU C176 PREASSESSMENT, WGU C176 PRACTICE TESTS A & B AND WGU C176 POST ASSESSMENT| 580 QS AND CORRECT ANSWERS (GUARANTEED PASS) $34.99   Add to cart

Exam (elaborations)

WGU C176 EXAM PREPARATION TEST BANK 2025 CONTAINS WGU C176 QUIZZES, WGU C176 PREASSESSMENT, WGU C176 PRACTICE TESTS A & B AND WGU C176 POST ASSESSMENT| 580 QS AND CORRECT ANSWERS (GUARANTEED PASS)

 0 view  0 purchase
  • Course
  • WGU C176 PROJECT MANAGEMENT
  • Institution
  • WGU C176 PROJECT MANAGEMENT

WGU C176 EXAM PREPARATION TEST BANK 2025 CONTAINS WGU C176 QUIZZES, WGU C176 PREASSESSMENT, WGU C176 PRACTICE TESTS A & B AND WGU C176 POST ASSESSMENT| 580 QS AND CORRECT ANSWERS (GUARANTEED PASS)

Preview 4 out of 190  pages

  • November 20, 2024
  • 190
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • WGU C176 PROJECT MANAGEMENT
  • WGU C176 PROJECT MANAGEMENT
avatar-seller
muriithikelvin098
WGU C176 EXAM PREPARATION TEST BANK 2025
CONTAINS WGU C176 QUIZZES, WGU C176 PRE-
ASSESSMENT, WGU C176 PRACTICE TESTS A & B
AND WGU C176 POST ASSESSMENT| 580 QS AND
CORRECT ANSWERS (GUARANTEED PASS)


WGU C176 QUIZZES
(200 QUESTIONS)
What is the definition of a project? Choose two.
A A process used to generate profit, improve market share, or adhere to legal
requirements
B A temporary endeavor undertaken to create a unique product, service, or result
C Through the use of project management techniques, which are repeatable
processes, a series of actions that are performed to produce the same result
multiple times
D A group of interrelated activities that create a unique benefit to the organization
E A time-constrained endeavor with assigned resources responsible for meeting the
goals according to the quality standards - ANSWER-A temporary endeavor
undertaken to create a unique product, service, or result
A time-constrained endeavor with assigned resources responsible for meeting the
goals according to the quality standards


Your project has expected cash inflows of $1.2 million in year 1, $2.4 million in
year 2, and $4.6 million in year 3. The project pays for itself in 23 months. Which
cash flow technique was used to determine this?
A Payback period
B IRR
C NPV


pg. 1

,D Discounted cash flow - ANSWER-Payback period


A key responsibility of the project manager includes informing this person of
changes, status, conflicts, and issues on the project.
A The project coordinator
B The project sponsor
C The project requestor
D The most influential project stakeholder - ANSWER-The project sponsor


Jack is a key stakeholder on the project. He's a big believer in the benefits of the
project and provides enthusiasm, energy, communication, and motivation for your
project. What is Jack's role?
A Project stakeholder
B Project champion
C Project team member
D Business analyst - ANSWER-Project champion


Which stakeholder assigns employees to the project in the matrix organization?
A Functional manager
B Project manager
C Sponsor
D Customer - ANSWER-Functional manager


Your project has expected cash inflows of $7.8 million in today's dollars. The
project's initial investment is $9.2 million. Which of the following is true?
A NPV is less than zero, so this project should be rejected.



pg. 2

,B The discounted cash flows are lower than the initial investment, so this project
should be accepted.
C The discounted cash flows are lower than the initial investment, so this project
should be rejected.
D NPV is greater than zero, so this project should be accepted. - ANSWER-NPV is
less than zero, so this project should be rejected.


A project manager has the most authority under which organizational structure?
A Functional
B Projectized
C Strong matrix
D Balanced matrix - ANSWER-Projectized


You are working in a matrix organization. Choose the responses that describe this
type of structure.


A Matrix organizations can be structured as strong, weak, or balanced.
B Project managers and functional managers share authority levels.
C Matrix organizations typically are organized along departmental lines, like a
functional organization.
D Employees are assigned project tasks by their project manager in this type of
structure.
E Resources are assigned to the project within their respective functional areas by a
project manager. - ANSWER-Matrix organizations can be structured as strong,
weak, or balanced.
Project managers and functional managers share authority levels.
Matrix organizations typically are organized along departmental lines, like a
functional organization.


pg. 3

, Employees are assigned project tasks by their project manager in this type of
structure.


You've been given an idea for a project by an executive in your organization. After
writing the business-case analysis, you submit it to the executive for review. After
reading the business case, he determines that the project poses a significant amount
of risk to the organization. What do you recommend next?
A Perform a feasibility study.
B Proceed to the project selection committee.
C Reject the project based on the analysis.
D Proceed to writing the project plan. - ANSWER-Perform a feasibility study.


What is the term for a group of related projects managed in a coordinated fashion?
A Process group
B Phase
C Life cycle
D Program - ANSWER-Program


Which of the following are the steps required to validate a project?
Each correct answer represents a complete solution. Choose all that apply.


A Validate the business case.
B Align it to the strategic plan.
C Justify the project.
D Validate the project management plan.
E Identify and analyze stakeholders. - ANSWER-Validate the business case.
Align it to the strategic plan.

pg. 4

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller muriithikelvin098. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $34.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

75057 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$34.99
  • (0)
  Add to cart