Which attribute most accurately describes a project?-The correct answer is:
| | | | | | | | |
Projects are finite.
| | |
What is an example of how project managers apply sound management
| | | | | | | | | |
techniques?-The correct answer is: they break down a task further if it remains
| | | | | | | | | | | | |
at the same percent completion despite reported progress.
| | | | | | | |
Which is an advantage of using a standardized project management model?-
| | | | | | | | | |
The correct answer is: The model is a framework that project managers can
| | | | | | | | | | | |
adapt to project specifics.
| | | |
In the project model, what do outputs from the Plan phase become?-The
| | | | | | | | | | |
|correct answer is: inputs to the Execute phase.
| | | | | | |
A project will have a long payback period. What should the project be linked to
| | | | | | | | | | | | | |
thus increasing the chances the project will be approved?-The correct answer
| | | | | | | | | | |
is: Strategic facility plans
| | | |
Which activity is set by policy at the start of a project?-The correct answer is:
| | | | | | | | | | | | | |
Estimating
|
What should a facility manager do at the beginning of a routine project to
| | | | | | | | | | | | |
achieve success?-The correct answer is: generate a shared understanding of
| | | | | | | | | |
the end purpose of a project.
| | | | | |
,What principle is true about the steps involved when defining project success?-
| | | | | | | | | | |
The correct answer is: Specifying nonessential parameters is as important as
| | | | | | | | | |
specifying essential ones.
| | |
Which document may include details such as adjacency diagrams, space
| | | | | | | | |
standards, and information on current and future staffing count for business
| | | | | | | | | | |
units?-The correct answer is: Statement of requirements
| | | | | | |
In what document would the project manager be formally listed?-The correct
| | | | | | | | | |
|answer is: Project charter | | |
Which is true about the elements in a project objectives statement?-The
| | | | | | | | | |
correct answer is: Schedule documentation only includes milestones for hard
| | | | | | | | | |
delivery dates.
| |
An organization gathers data on occupant space requirements, desired location,
| | | | | | | | |
and desired cost per square meter (square foot). What other factors should be
| | | | | | | | | | | | |
considered when listing site selection criteria?-The correct answer is: Desired
| | | | | | | | | |
floor plan/stacking plan and desired amenities
| | | | | |
Which element is developed first?-The correct answer is: Work Breakdown
| | | | | | | | |
Structure (WBS)
| |
Of the following terms related to a WBS, which statement is correct?-The
| | | | | | | | | | |
correct answer is: A task is a function to be performed that is detailed enough
| | | | | | | | | | | | | | |
for proposals to indicate cost, schedule, and readiness and completion criteria.
| | | | | | | | | | |
, In which scheduling methods are as many activities as possible concurrently
| | | | | | | | | |
|performed?-The correct answer is: Waterfall model scheduling
| | | | | |
Which statement is true of communications management for an office
| | | | | | | | |
relocation?-The correct answer is: Post-relocation orientation brochures can
| | | | | | | |
help employees find their way around.
| | | | | |
Which role helps ensure continued senior management/client support of major
| | | | | | | | |
projects?-The correct answer is: Project champion
| | | | | |
Which statement is true of contract details?-The correct answer is: Non typical
| | | | | | | | | | |
materials or installation methods should not be included in the main body of a
| | | | | | | | | | | | | |
contractor's proposal.
| |
Which pre-project actions reduce risk and increase the probability of project
| | | | | | | | | |
success?-The correct answer is: Pre-select contractors
| | | | | |
If an organization has narrowed the list of contractors submitting proposals but
| | | | | | | | | | |
|is still having trouble deciding between them, what could help?-The correct
| | | | | | | | | |
|answer is: Bidder presentations
| | |
Which statement is true of the Execute, Monitor and Control phases of the
| | | | | | | | | | | |
project model?-The correct answer is: These phases are often concurrently or
| | | | | | | | | | |
iteratively performed.
| |
When project managers determine the level of data to collect for monitoring
| | | | | | | | | | |
and controlling project work, what do they not need to verify?-The correct
| | | | | | | | | | | |
answer is: Project work delays due to data collection are scheduled.
| | | | | | | | | | |
| | | | | | | | |
Projects are finite.
| | |
What is an example of how project managers apply sound management
| | | | | | | | | |
techniques?-The correct answer is: they break down a task further if it remains
| | | | | | | | | | | | |
at the same percent completion despite reported progress.
| | | | | | | |
Which is an advantage of using a standardized project management model?-
| | | | | | | | | |
The correct answer is: The model is a framework that project managers can
| | | | | | | | | | | |
adapt to project specifics.
| | | |
In the project model, what do outputs from the Plan phase become?-The
| | | | | | | | | | |
|correct answer is: inputs to the Execute phase.
| | | | | | |
A project will have a long payback period. What should the project be linked to
| | | | | | | | | | | | | |
thus increasing the chances the project will be approved?-The correct answer
| | | | | | | | | | |
is: Strategic facility plans
| | | |
Which activity is set by policy at the start of a project?-The correct answer is:
| | | | | | | | | | | | | |
Estimating
|
What should a facility manager do at the beginning of a routine project to
| | | | | | | | | | | | |
achieve success?-The correct answer is: generate a shared understanding of
| | | | | | | | | |
the end purpose of a project.
| | | | | |
,What principle is true about the steps involved when defining project success?-
| | | | | | | | | | |
The correct answer is: Specifying nonessential parameters is as important as
| | | | | | | | | |
specifying essential ones.
| | |
Which document may include details such as adjacency diagrams, space
| | | | | | | | |
standards, and information on current and future staffing count for business
| | | | | | | | | | |
units?-The correct answer is: Statement of requirements
| | | | | | |
In what document would the project manager be formally listed?-The correct
| | | | | | | | | |
|answer is: Project charter | | |
Which is true about the elements in a project objectives statement?-The
| | | | | | | | | |
correct answer is: Schedule documentation only includes milestones for hard
| | | | | | | | | |
delivery dates.
| |
An organization gathers data on occupant space requirements, desired location,
| | | | | | | | |
and desired cost per square meter (square foot). What other factors should be
| | | | | | | | | | | | |
considered when listing site selection criteria?-The correct answer is: Desired
| | | | | | | | | |
floor plan/stacking plan and desired amenities
| | | | | |
Which element is developed first?-The correct answer is: Work Breakdown
| | | | | | | | |
Structure (WBS)
| |
Of the following terms related to a WBS, which statement is correct?-The
| | | | | | | | | | |
correct answer is: A task is a function to be performed that is detailed enough
| | | | | | | | | | | | | | |
for proposals to indicate cost, schedule, and readiness and completion criteria.
| | | | | | | | | | |
, In which scheduling methods are as many activities as possible concurrently
| | | | | | | | | |
|performed?-The correct answer is: Waterfall model scheduling
| | | | | |
Which statement is true of communications management for an office
| | | | | | | | |
relocation?-The correct answer is: Post-relocation orientation brochures can
| | | | | | | |
help employees find their way around.
| | | | | |
Which role helps ensure continued senior management/client support of major
| | | | | | | | |
projects?-The correct answer is: Project champion
| | | | | |
Which statement is true of contract details?-The correct answer is: Non typical
| | | | | | | | | | |
materials or installation methods should not be included in the main body of a
| | | | | | | | | | | | | |
contractor's proposal.
| |
Which pre-project actions reduce risk and increase the probability of project
| | | | | | | | | |
success?-The correct answer is: Pre-select contractors
| | | | | |
If an organization has narrowed the list of contractors submitting proposals but
| | | | | | | | | | |
|is still having trouble deciding between them, what could help?-The correct
| | | | | | | | | |
|answer is: Bidder presentations
| | |
Which statement is true of the Execute, Monitor and Control phases of the
| | | | | | | | | | | |
project model?-The correct answer is: These phases are often concurrently or
| | | | | | | | | | |
iteratively performed.
| |
When project managers determine the level of data to collect for monitoring
| | | | | | | | | | |
and controlling project work, what do they not need to verify?-The correct
| | | | | | | | | | | |
answer is: Project work delays due to data collection are scheduled.
| | | | | | | | | | |