100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
TEST BANK For Information Technology Project Management 9th Edition by Kathy Schwalbe, Verified Chapters 1 - 13, Complete Newest Version $14.49
Add to cart

Exam (elaborations)

TEST BANK For Information Technology Project Management 9th Edition by Kathy Schwalbe, Verified Chapters 1 - 13, Complete Newest Version

 0 view  0 purchase
  • Course
  • Information Technology Project Mana
  • Institution
  • Information Technology Project Mana

TEST BANK For Information Technology Project Management 9th Edition by Kathy Schwalbe, Verified Chapters 1 - 13, Complete Newest VersionTEST BANK For Information Technology Project Management 9th Edition by Kathy Schwalbe, Verified Chapters 1 - 13, Complete Newest VersionTEST BANK For Information T...

[Show more]

Preview 4 out of 648  pages

  • January 6, 2025
  • 648
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
book image

Book Title:

Author(s):

  • Edition:
  • ISBN:
  • Edition:
  • Information Technology Project Mana
  • Information Technology Project Mana
avatar-seller
knowledgeNest
TEST BANK For Information Technology
a a a a




a Project Management 9th Edition
a a a a




Kathy Schwalbe, Verified Chapters
a a a




Page a1 aof a
648

,True a/ aFalse

1. Until athe a1980s, aproject amanagement aprimarily afocused aon aproviding aschedule aand aresource adata
ato atop amanagement ain athe amilitary, acomputer, aand aconstruction aindustries.

a. True
b. False
ANSWER: True
RATIONALE: Feedback: aUntil athe a1980s, aproject amanagement aprimarily afocused aon
aproviding aschedule aand aresource adata ato atop amanagement ain athe amilitary,
acomputer, aand aconstruction aindustries. aToday’s aproject amanagement
ainvolves amuch amore, aand apeople ain aevery aindustry aand aevery acountry

amanage aprojects.

POINTS: 1
DIFFICULTY: Difficulty: aEasy
REFERENCES: p.2
LEARNING aOBJECTIVES: INFO.SCHW.14.1 a- aLO: a1-1
NATIONAL aSTANDARDS: United aStates a- aBUSPROG: aTechnology
TOPICS: Introduction
KEYWORDS: Bloom's: aKnowledge


2. A adifference abetween aoperations aand aprojects ais athat aoperations aend awhen atheir aobjectives ahave
abeen areached, awhereas aprojects ado anot.

a. True
b. False
ANSWER: False
RATIONALE: Feedback: aProjects aare adifferent afrom aoperations ain athat athey aend awhen
their aobjectives ahave abeen areached aor athe aproject ahas abeen aterminated.
a


POINTS: 1
DIFFICULTY: Difficulty: aModerate
REFERENCES: p.4
LEARNING aOBJECTIVES: INFO.SCHW.14.2 a- aLO: a1-2
NATIONAL aSTANDARDS: United aStates a- aBUSPROG: aAnalytic
TOPICS: What ais aa aProject?
KEYWORDS: Bloom's: aComprehension


3. Every aproject ashould ahave aa awell-defined aobjective.
a. True




Page a2 aof a
648

,2



b. False
ANSWER: True
RATIONALE: Feedback: aA aproject ahas aa aunique apurpose. aEvery aproject ashould ahave aa awell-
defined aobjective.
POINTS: 1
DIFFICULTY: Difficulty: aEasy
REFERENCES: p.6
LEARNING aOBJECTIVES: INFO.SCHW.14.2 a- aLO: a1-2
NATIONAL aSTANDARDS: United aStates a- aBUSPROG: aAnalytic
TOPICS: What ais aa aProject?
KEYWORDS: Bloom's: aKnowledge


4. Projects ashould abe adeveloped ain aincrements.
a. True
b. False
ANSWER: True
RATIONALE: Feedback: aA aproject ais adeveloped ausing aprogressive aelaboration. aProjects aare
aoften adefined abroadly awhen athey abegin, aand aas atime apasses, athe aspecific
adetails aof athe aproject abecome aclearer. aTherefore, aprojects ashould abe
adeveloped ain aincrements.

POINTS: 1
DIFFICULTY: Difficulty: aModerate
REFERENCES: p.6
LEARNING aOBJECTIVES: INFO.SCHW.14.2 a- aLO: a1-2
NATIONAL aSTANDARDS: United aStates a- aBUSPROG: aAnalytic
TOPICS: What ais aa aProject?
KEYWORDS: Bloom's: aComprehension


5. Resources ain aa aproject ashould abe aused aeffectively abecause athey aare alimited.
a. True
b. False
ANSWER: True
RATIONALE: Feedback: aA aproject arequires aresources, aoften afrom avarious aareas.
aResources, ahowever, aare alimited aand amust abe aused aeffectively ato ameet
aproject aand aother acorporate agoals.
POINTS: 1
DIFFICULTY: Difficulty: aModerate
REFERENCES: p. a7
LEARNING aOBJECTIVES: INFO.SCHW.14.2 a- aLO: a1-2
NATIONAL aSTANDARDS: United aStates a- aBUSPROG: aAnalytic
TOPICS: What ais aa aProject?
KEYWORDS: Bloom's: aComprehension

Page a3 aof a
648

, 3



6. A aproject amanager’s aprimary arole ais ato aprovide athe afunding afor aa aproject.
a. True
b. False
ANSWER: False
RATIONALE: Feedback: aA aproject asponsor ausually aprovides athe adirection aand afunding afor aa
project.
a

POINTS: 1
DIFFICULTY: Difficulty: aEasy
REFERENCES: p.7
LEARNING aOBJECTIVES: INFO.SCHW.14.2 a- aLO: a1-2
NATIONAL aSTANDARDS: United aStates a- aBUSPROG: aAnalytic
TOPICS: What ais aa aProject?
KEYWORDS: Bloom's: aKnowledge


7. One aof athe amain areasons awhy aproject amanagement ais achallenging ais abecause aof athe afactor aof
auncertainty.

a. True
b. False
ANSWER: True
RATIONALE: Feedback: aA aproject ainvolves auncertainty. aEvery aproject ais aunique aand athus ait
ais asometimes adifficult ato adefine aits aobjectives aclearly, aestimate ahow along ait awill
atake ato acomplete, aor adetermine ahow amuch ait awill acost. aThis auncertainty ais
aone aof athe amain areasons aproject amanagement ais aso achallenging.

POINTS: 1
DIFFICULTY: Difficulty: aModerate
REFERENCES: p.7
LEARNING aOBJECTIVES: INFO.SCHW.14.2 a- aLO: a1-2
NATIONAL aSTANDARDS: United aStates a- aBUSPROG: aAnalytic
TOPICS: What ais aa aProject?
KEYWORDS: Bloom's: aComprehension


8. Questions aabout ahow aa ateam awill atrack aschedule aperformance ais arelated ato aa aproject’s ascope.
a. True
b. False
ANSWER: False
RATIONALE: Feedback: aProject ascope adeals awith aquestions asuch aas, a“What awork awill abe
adone aas apart aof athe aproject?”, a“What aunique aproduct, aservice, aor aresult adoes
athe acustomer aor asponsor aexpect afrom athe aproject?”, aor a“How awill athe ascope
abe averified?”

POINTS: 1
DIFFICULTY: Difficulty: aModerate
REFERENCES: p.7
LEARNING aOBJECTIVES: INFO.SCHW.14.2 a- aLO: a1-2
Page a3 aof a
648

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller knowledgeNest. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $14.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

51683 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 15 years now

Start selling
$14.49
  • (0)
Add to cart
Added