1. FOB freight prepaid requires __________ to pay for shipping charges. A. Contractor B. Buyer C. Seller D. Subcontractor - Answer Seller 2. Which of the following is not a member of the supervisory? A. Foreman B. materials expediter C. Owner's representative D. Project manager - Answer...