[Show more]Which of the following tools should be used when a team is generating and prioritizing a 
list of options that include highly controversial issues? 
A.) Brainstorming 
B.) Affinity Diagrams 
C.) Nominal group technique 
D.) 5 Why 
: C.) Nominal group technique 
The primary factor in the successful ...
Preview 2 out of 14 pages
Add to cartWhich of the following tools should be used when a team is generating and prioritizing a 
list of options that include highly controversial issues? 
A.) Brainstorming 
B.) Affinity Diagrams 
C.) Nominal group technique 
D.) 5 Why 
: C.) Nominal group technique 
The primary factor in the successful ...
Which of the following is not an important element of a gage calibration program? 
A) Systematic follow-up on scheduled calibrations. 
B) Track individual instruments with unique serial numbers. 
C) Ensure use of most advanced measurement technology. 
D) Provide trace-ability of standards to NIST (o...
Preview 2 out of 6 pages
Add to cartWhich of the following is not an important element of a gage calibration program? 
A) Systematic follow-up on scheduled calibrations. 
B) Track individual instruments with unique serial numbers. 
C) Ensure use of most advanced measurement technology. 
D) Provide trace-ability of standards to NIST (o...
Which of the following is NOT a reason to use continuous (variable) data? 
A) It provides a better measure of variation. 
B) It is more convenient for subjective appearance items. 
C) A greater number of statistical analysis tools can be applied. 
D) There is less subjectivity involved. 
: B) It is ...
Preview 2 out of 6 pages
Add to cartWhich of the following is NOT a reason to use continuous (variable) data? 
A) It provides a better measure of variation. 
B) It is more convenient for subjective appearance items. 
C) A greater number of statistical analysis tools can be applied. 
D) There is less subjectivity involved. 
: B) It is ...
Which of the following is the primary reason for a project team to consider closing out 
the project? 
A) Product or service has been launched 
B) Customer requirements have been met 
C) Budget has been expended 
D) Timeline calls for project close-out 
E) Project team has disbanded 
: B) Customer ...
Preview 2 out of 7 pages
Add to cartWhich of the following is the primary reason for a project team to consider closing out 
the project? 
A) Product or service has been launched 
B) Customer requirements have been met 
C) Budget has been expended 
D) Timeline calls for project close-out 
E) Project team has disbanded 
: B) Customer ...
A researcher believes that Drug A is more effective (has a larger mean) than Drug B. 
What is an appropriate alternative hypothesis for any test he may conduct (note: µ = 
mean)? 
A) µ A > µ B 
B) µ A - µ B > 0 
C) µ B < µ A 
D) All of the above 
E) None of the above 
: D) All of t...
Preview 2 out of 8 pages
Add to cartA researcher believes that Drug A is more effective (has a larger mean) than Drug B. 
What is an appropriate alternative hypothesis for any test he may conduct (note: µ = 
mean)? 
A) µ A > µ B 
B) µ A - µ B > 0 
C) µ B < µ A 
D) All of the above 
E) None of the above 
: D) All of t...
Which of the following is a Supporting Service Requirement (vs. Primary Output 
Requirement)? 
A) Order-entry is efficient and customer-friendly. 
B) Delivery is provided quickly and with no issues. 
C) Product or service provided performs as specified. 
D) Quality concerns from customers are handl...
Preview 2 out of 5 pages
Add to cartWhich of the following is a Supporting Service Requirement (vs. Primary Output 
Requirement)? 
A) Order-entry is efficient and customer-friendly. 
B) Delivery is provided quickly and with no issues. 
C) Product or service provided performs as specified. 
D) Quality concerns from customers are handl...
What is the primary approach employed by Lean Six Sigma to reduce the number of 
defects? 
A) Add inspection to isolate the customer from process instability. 
B) Reduce process variability at the source through redesign or process controls. 
C) Revise specifications to better reflect customer exp...
Preview 2 out of 6 pages
Add to cartWhat is the primary approach employed by Lean Six Sigma to reduce the number of 
defects? 
A) Add inspection to isolate the customer from process instability. 
B) Reduce process variability at the source through redesign or process controls. 
C) Revise specifications to better reflect customer exp...
What are the 4 perspectives most commonly associated with the Balanced Scorecard? 
A) Financial, Marketing, Internal Processes, Technology 
B) Financial, Sales, Business Processes, People & Learning 
C) Corporate, Customer, Operations, Human Resources 
D) Financial, Customer, Internal Processes, Peo...
Preview 1 out of 4 pages
Add to cartWhat are the 4 perspectives most commonly associated with the Balanced Scorecard? 
A) Financial, Marketing, Internal Processes, Technology 
B) Financial, Sales, Business Processes, People & Learning 
C) Corporate, Customer, Operations, Human Resources 
D) Financial, Customer, Internal Processes, Peo...
All of the following are deliverables of the Define phase EXCEPT _____. 
(A.) Project Y in Y=f(x) 
(B.) Expected benefits 
(C.) Problem and goal statements 
(D.) List of Solutions 
: (D.) List of Solutions 
(TRUE or FALSE) Cost of Poor Quality (COPQ) reduction targeted by the project should 
be qua...
Preview 3 out of 16 pages
Add to cartAll of the following are deliverables of the Define phase EXCEPT _____. 
(A.) Project Y in Y=f(x) 
(B.) Expected benefits 
(C.) Problem and goal statements 
(D.) List of Solutions 
: (D.) List of Solutions 
(TRUE or FALSE) Cost of Poor Quality (COPQ) reduction targeted by the project should 
be qua...
A Lean Six Sigma team is working on a project to accelerate the collection of accounts 
receivable. The team wants to identify and eliminate process steps that are redundant 
or wasteful so that the overall cycle time can be improved. What type of process map 
would be the best choice? 
A) SIPOC ...
Preview 1 out of 3 pages
Add to cartA Lean Six Sigma team is working on a project to accelerate the collection of accounts 
receivable. The team wants to identify and eliminate process steps that are redundant 
or wasteful so that the overall cycle time can be improved. What type of process map 
would be the best choice? 
A) SIPOC ...
A pharmacy performed an FMEA on the prescription preparation process. One element 
of the process had an RPN much higher than the others. Which statement is true? 
A) The element with a high RPN indicates conformance with safety standards. 
B) The process element with a high RPN is the most reliabl...
Preview 2 out of 8 pages
Add to cartA pharmacy performed an FMEA on the prescription preparation process. One element 
of the process had an RPN much higher than the others. Which statement is true? 
A) The element with a high RPN indicates conformance with safety standards. 
B) The process element with a high RPN is the most reliabl...
What's Contained on the Charter? 
: Problem Description, Scope, Project Goals, Customer Benefits, 
Ownership/Team, Stakeholder Approval, Schedule 
What are the Three Pillars of PE? 
: Lean, DMAIIC, DMADV 
What is used to set Specification Limits? 
: Customer requirements 
What is the difference be...
Preview 3 out of 26 pages
Add to cartWhat's Contained on the Charter? 
: Problem Description, Scope, Project Goals, Customer Benefits, 
Ownership/Team, Stakeholder Approval, Schedule 
What are the Three Pillars of PE? 
: Lean, DMAIIC, DMADV 
What is used to set Specification Limits? 
: Customer requirements 
What is the difference be...
A Lean Six Sigma team at an insurance company has been working on a project to 
reduce the number of claim defects leading to denied claims. A control chart of claim 
denials is out-of-control. What conclusion should the team draw from this condition? 
A) The number of denials has gone up. 
B) The...
Preview 2 out of 6 pages
Add to cartA Lean Six Sigma team at an insurance company has been working on a project to 
reduce the number of claim defects leading to denied claims. A control chart of claim 
denials is out-of-control. What conclusion should the team draw from this condition? 
A) The number of denials has gone up. 
B) The...
SWOT is an acronym for: 
: strengths, weaknesses, opportunities, threats 
In a series of linked processes and associated feedback loops the product or service 
flows ________ and the information flows ___ 
: downstream, upstream 
A team has been asked to reduce the cycle time for a process. The tea...
Preview 2 out of 8 pages
Add to cartSWOT is an acronym for: 
: strengths, weaknesses, opportunities, threats 
In a series of linked processes and associated feedback loops the product or service 
flows ________ and the information flows ___ 
: downstream, upstream 
A team has been asked to reduce the cycle time for a process. The tea...
A Lean Six Sigma team is trying out a new forming tool to reduce variability in a process 
that creates hamburgers patties in a fast food restaurant. One of the significant 
dimensions has a process standard deviation of 0.35 mm. The team needs to know how 
many samples to collect in order to ach...
Preview 2 out of 5 pages
Add to cartA Lean Six Sigma team is trying out a new forming tool to reduce variability in a process 
that creates hamburgers patties in a fast food restaurant. One of the significant 
dimensions has a process standard deviation of 0.35 mm. The team needs to know how 
many samples to collect in order to ach...
The next several questions are based on analysis of the dataset download provided on 
the course page where you launched the quiz module. The data are from a 2-level full 
factorial experiment with 2 replicates to evaluate the effect of three factors, A, B and C 
on the life of a product. Analyze...
Preview 2 out of 8 pages
Add to cartThe next several questions are based on analysis of the dataset download provided on 
the course page where you launched the quiz module. The data are from a 2-level full 
factorial experiment with 2 replicates to evaluate the effect of three factors, A, B and C 
on the life of a product. Analyze...
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Stuvia is a marketplace, so you are not buying this document from us, but from seller ExamArsenal. Stuvia facilitates payment to the seller.
No, you only buy these notes for $20.49. You're not tied to anything after your purchase.
4.6 stars on Google & Trustpilot (+1000 reviews)
67096 documents were sold in the last 30 days
Founded in 2010, the go-to place to buy study notes for 14 years now