2021/2022
A milestone task on the critical path has been completed.
which of the following should the project manager notify?
A owner of predecessor task
B project team
C project sponsor
D project steering committee correct answer- C
During a project assessment, a project manager determines the initial project cost
estimates were incorrect oh, and there is not enough budget left, including reserves, to
complete the project.
Which of the following actions should the project manager take?
A alert the project sponsor of the situation
B contact the customer and request more funding
C announce the project will end due to lack of funds
D attempt to save money in downstream activities correct answer- A
Which of the following is the primary purpose of an MOA or an mou?
A State expectations of all signatory parties to reduce potential misunderstandings
B facilitate potential legal action and resulting remediation if one of the signatory parties
violate any terms
C enumerate a detail code of conduct for all employees, contractors, and
subcontractors participating in the program.
D provide transparency to competitors regarding all signatory parties correct answer- A
two team members have concluded that documentation is not required due to the size
of the current project. The project manager has encouraged them to align strictly with
the process.
which of the following conflict resolution techniques has the project manager utilized?
,A smoothing
B forcing
C compromising
D avoiding correct answer- B
The client accepts the critical design review.
which of the following meetings should be held to move to the next step in the project?
A execution
B kickoff
C closure
D planning correct answer- B
A project manager is working on the project charter.
Which of the following phases does this describe?
A initiation
B planning
C execution
D closing correct answer- A
A project in the execution phase is over budget, and tasks on the critical path are on
schedule.
Which of the following should the project manager do next?
A update the project management plan
B issue a change request
C revise the project charter
D evaluate the impact to the baseline correct answer- D
Several team members report that meeting objectives are not being met.
which of the following documents would a project manager free to make team meetings
more effective? Choose two
1 create an s o w prior to each meeting and adhere to it
2 create a meeting agenda prior to each meeting and adhere to it
3 create a lessons learned list prior to each meeting and adhere to it
4 create a project charter prior to each meeting and adhere to it
5 create an action item list during the meeting and adhere to it
6 create a corrective action plan prior to each meeting and adhere to it
7 create a WBS prior to each meeting and adhere to it
,A 2,5
B 1,4 correct answer- A
Which of the following documents should be used prior to high-level recording to key
stakeholders?
A dashboard
B communication plan
C statement of work
D project charter correct answer- A
A new project charter is being drafted.
which of the following would be the best source for the high-level project requirements?
A sponsor
B project manager
C project management office
D project team correct answer- A
Which of the following project document should be used to record the occurrence of an
unplanned event?
A action log
B risk log
C change log
D issue log correct answer- D
Which of the following documents does offender rely most before committing funding
and resources to a project?
A SOW
B PO
C SLA
D MOU correct answer- A
which of the following measurements would give the project manager the best estimate
of the total cost of an active project?
A EAC
B BAC
C TCPI
D ETC correct answer- A
A customer will have ongoing changes to project requirements.
, which of the following is the best project management methodology for this
requirement?
A waterfall
B agile
C PRINCE2
D BOTTOM UP correct answer- B
Which of the following describes risk mitigation?
A the transfer of the risk to another entity or project inside or outside the organization,
along with the associated costs.
B the understanding of the risks with a detailed explanation and how to project intends
to address the potential for occurrence.
C the quantification of the risk in terms of how much the risk of potentially cost the
project or parent organization.
D The waiting or privatization of the risk against all of their identified risks within this
project or others associated with it. correct answer- B
Which of the following is a definition of an RFP?
A a document sent to potential vendors to solicit a bid for a project.
B a document sent a potential vendors to request information for skills and experience
for a project.
C a document sent to potential vendors to request a commitment for a project.
D a document cents potential vendors to solicit information that excludes pricing
information for a project. correct answer- A
A customer has requested additional features for an active project.
which of the following steps should take place next?
A implement the requested changes
B evaluate the impact of the changes
C update all project documents
D submit the requested changes to the CCB correct answer- B
A project manager has an opportunity to add highly skilled expert to the team who can
increase the probability of the project success.