100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
Summary of the chapter 16 'managing cost and earned value' from Gower Handbook of project management $4.01   Add to cart

Summary

Summary of the chapter 16 'managing cost and earned value' from Gower Handbook of project management

1 review
 24 views  0 purchase
  • Course
  • Institution
  • Book

Summary of the chapter 16 'managing cost and earned value' from Gower Handbook of project management

Preview 2 out of 8  pages

  • Unknown
  • March 31, 2023
  • 8
  • 2022/2023
  • Summary

1  review

review-writer-avatar

By: ddano1995 • 6 months ago

avatar-seller
Summary of the hand of project management | Remco van der Schoot


16. CHAPTER 16 – MANAGING COST AND EARNED VAL UE (P.247-263)
Earned Value Management (EVM) = a methodology used to measure and communicate the real physical progress
of a project and to integrate the three critical elements of project management (scope, time and cost
management). It takes into account the following factors:
➢ the work completed.
➢ the time taken.
➢ the costs incurred to complete the project.

16.1. MANAGING COSTS
Project performance should be measured throughout the entire life of the project at regular time intervals. The
ideal point of reference is a fixed time frame known as the baseline schedule of the project. Having knowledge
about activity costs, this baseline schedule can be translated into a time-phased planned value for each activity
and for the total project.
➢ The baseline schedule of the project can be constructed with project scheduling techniques such as he
critical path method (CPM) and defines start times (and finish times) for each project activity.


16.1.1. KEY METRICS
The planned duration (PD) = the total project duration as a result of the constructed CPM schedule or its resource
related extensions and is often referred to as schedule at completion (SAC)
The actual time (AT) = the number of time periods (for example, weeks) the project is in progress at the current
time instance.
The real duration (RD) = the real final project duration known upon the project’s finish.
The budget at completion (BAC) = the sum of all budgeted costs for the individual activities

The Planned Value (PV) = the time-phased budget baseline as an immediate translation of the schedule
constructed from the project network using well-known CPM project scheduling techniques and measures how
much value should have been earned according to the baseline schedule.
➢ The cumulative increase in the total budgeted activity cost given the start and finish times stipulated in
the baseline schedule.
➢ The PV is often called budgeted cost of work scheduled (BCWS).




Each activity has a duration of one week and a budgeted cost of €20,000, leading to a schedule with PD = 5 weeks
and a total expected cost of BAC = €100,000. The translation of the baseline schedule displayed at the top of
Figure 16.1 into monetary terms leads to the PV curve as displayed in the figure.

P a g i n a 29 | 53

, Summary of the hand of project management | Remco van der Schoot



Actual Cost (AC) or actual cost of work performed (ACWP) = cumulative actual cost spent at a given point AT in
time and measures the actual cost incurred up to the current time.

Earned Value (EV) or budgeted cost of work performed (BCWP) = the amount budgeted for performing the work
that was accomplished at a given point AT in time and measures how much value has been earned at the current
time.
➢ Equals the total activity (or project) BAC multiplied by the percentage activity (or project) completion
(PC) at the particular point in time (= PC * BAC).




The following conclusions can be made:
➢ Since the baseline schedule (PV) stipulates that €5,000 more should have been earned than actually
earned (EV) at week 3, the project is clearly late.
➢ Since the value of the work done up to now (AC) exceeds the value that should have been earned with
that current work done as stipulated in the baseline schedule (EV), the project is clearly over budget


16.1.2. PERFORMANCE MEASURMENTS
Time and cost deviations (underruns and overruns) can be expressed by variances or unitless indicators, as
discussed in the two following sections.

Variances: Project performance, both in terms of time and cost, is determined by comparing the three key
parameters PV, AC and EV, resulting in two well-known performance variances:
➢ Schedule variance -> (SV = EV − PV)
o = 0: project on schedule
o < 0: project delay
o > 0: project ahead of schedule

P a g i n a 30 | 53

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller RSCHO. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $4.01. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

76669 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$4.01
  • (1)
  Add to cart