An industry operating an 8-hour shift, 5 days per week, generates 100,000 gallons of wastewater per shift. Their pretreatment system has a capacity of 150 gallons per minute. How long must the pretreatment facility operate to process the wastewater generated each day? - 11.1 hours An industry ha...