100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
APM PMQ EXAM Complete Questions & Answers(Latest Update 2024) $12.99
Add to cart

Exam (elaborations)

APM PMQ EXAM Complete Questions & Answers(Latest Update 2024)

 652 views  2 purchases
  • Course
  • APM PMQ
  • Institution
  • APM PMQ

Configuration Management process - Status accounting - ANSWER knowing the status of items, proposed changes and the implementation status of approved changes (Archived records) Risk in a Business case - ANSWER the major risks and their impact on the business case. What a business case include...

[Show more]

Preview 3 out of 23  pages

  • January 4, 2024
  • 23
  • 2023/2024
  • Exam (elaborations)
  • Questions & answers
  • apm pmq
  • APM PMQ
  • APM PMQ
avatar-seller
suedocs
APM PMQ EXAM Complete Questions &
Answers(Latest Update 2024)
Configuration Management process - Status accounting - ANSWER knowing the status
of items, proposed changes and the implementation status of approved changes
(Archived records)

Risk in a Business case - ANSWER the major risks and their impact on the business
case.

What a business case includes? (BOBCART) - ANSWER Background, Options,
Benefits, Commercial Aspects, Risks, Timescales

PRAM process - ANSWER Initiate
Identify
Assess
Plan responses
Implement responses

Risk management - Initiate - ANSWER How the risk will be managed? (PMP, Risk
management plan)

Risk management - Assess - ANSWER how risky is each risk (Risk matrix, probability &
impact chart)

Risk management - Identify - ANSWER Use of Identification methods such as (risk logs,
brainstorming, meetings, Delphi)

Plan responses - ANSWER is this risk a threat or opportunity to the project? (SWAT
Analysis)

Implement - ANSWER when the risk is added to the project plan, (PMP, risk log, Gannt
chart)

Extended project life cycle - ANSWER Concept
Definition
Development
Handover and Closure
Operations
Benefits Realisation
Termination

,Who are potential stakeholders within a project? - ANSWER Project Sponsor, Project
Team, Users , Suppliers, Customers, Senior Management

Information management process - ANSWER Collection, Storage, Dissemination,
Archiving, Destruction

Requirements management process - Capture - ANSWER is a research exercise
undertaken early in a project to establish the scope and what is needed. (brainstorming,
prototypes, archived documentation)

What are the steps of the change control process? - ANSWER Submit Change, Review
change, Assess feasibility and impact, Decision

What is the requirements model? - ANSWER Business needs, features, requirements,
acceptance Criteria

What are the steps of the configuration management process? - ANSWER Planning,
Identification, Control, Status Accounting , Audit

What are 2 types of breakdown structure? - ANSWER WBS, OBS

What is a Work Breakdown Structure (WBS)? - ANSWER a comprehensive list of all
activities needed to complete a project.

What is a Product Breakdown Structure (PBS)? - ANSWER focuses on the deliverables
needed to deliver the project. This can be broken down further into tasks within a WBS.

What are 5 types of report? - ANSWER Progress
Quality
Risk
Finance
Audit

What are 3 types of investment appraisal? - ANSWER Net present value (NPV)
Payback
Internal Rate of Return (IRR)

What are the steps of the stakeholder management process? - ANSWER Identify
Assess
Develop
Engage

How do you calculate Earned Value (EV)? - ANSWER EV= %complete x Budget at
completion

, How do you calculate Cost Variance (CV)? - ANSWER CV= Earned Value - Actual
Costs

How do you calculate Schedule Variance (SV)? - ANSWER SV= Earned Value -
Planned Costs

How do you calculate Cost Performance Index (CPI)? - ANSWER CPI = Earned Value /
Actual Costs

How do you calculate Schedule Performance Index (SPI)? - ANSWER SPI = Earned
Value / Planned Costs

How do you calculate Estimate at completion - cost (EACc)? - ANSWER EACc= Budget
at Completion/Cost Performance Index

How do you calculate Estimate at completion - time (EACt)? - ANSWER EACt= Planned
Duration/Schedule Performance Index

What does Earned Value Management tell you? - ANSWER - Schedule
- Efficiency
- Time to completion
- Spend
- Cost to completion
- Actual forecast cost
- Variance at completion

What are the benefits of using Earned Value Management? - ANSWER - Reporting
- Estimating errors
- Forecasting
- Justify corrective action
- Justify early termination

What are 3 types of estimating tool? - ANSWER - Comparative
- Bottoms Up
- Parametric

What is Comparative estimating? - ANSWER Uses historical data to provide current
estimations

What is Bottoms up estimating? - ANSWER Detailed estimate produced for each work
package and then rolled-up throughout the WBS

What is parametric estimating? - ANSWER Uses statistical modelling software to
produce overall estimates for time and cost

What are problems with estimating? - ANSWER - Optimisim/Pessimism

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller suedocs. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $12.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

53068 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$12.99  2x  sold
  • (0)
Add to cart
Added