NICET Highway Construction Inspector Level III Practice Exam 1 (56 passed new update questions and answers)
23 views 1 purchase
Course
NICET Highway Construction Inspector
Institution
NICET Highway Construction Inspector
NICET Highway Construction Inspector Level III Practice Exam 1 (56 passed new update questions and answers)
During installation of traffic loops in the pavement, which three statements apply prior to and during the installation of loop wire? (Choose 3).
a) Do not allow vehicular traffic over an...
NICET Highway Construction Inspector Level III Practice Exam 1
(56 passed new update questions and answers) During installation of traffic loops in the pavement, which three statements apply prior to and during the installation of loop wire? (Choose 3).
a)Do not allow vehicular traffic over an open saw cut.
b)Do not overlap saw cuts at the corner.
c)Thoroughly clean the saw cut of foreign material.
d)Use a plastic sleeve where loop wire crosses a joint. - Answer a) Do not allow
vehicular traffic over an open saw cut.
c)Thoroughly clean the saw cut of foreign material.
d)Use a plastic sleeve where loop wire crosses a joint.
The contractor is installing a culvert with a 12-inch reinforced concrete pipe (
outside diameter of 16.50 inches) from Sta 10+00, 40 feet Left to STA 10+00, 65 feet Right on 4-inch bedding material. The 12-inch RCP outlet is to be installed at Sta 10+00, 40 feet Left at an invert elevation of 652.50. a)652.04
b)653.17If the conduit is installed at a 1.40% slope, what is the elevation of the foundation grade at Sta 10+00, 45 feet Right?
c)653.36
d)653.50 - Answer ?
On the reservoir side of a dam, erosion protection against wave action should extend up the slope to at least which level?
a)crest of dam
b)maximum water elevation
c)minimum water elevation
d)two-thirds the height of the dam - Answer b) maximum water elevation
During stage construction while installing drainage, the contractor must complete which two of the following tasks? (Choose two).
a)Bulk head the pipe until the system is complete.
b)Complete the entire system before it rains.
c)Maintain the existing drainage system until the new system is functional.
d)Provide temporary connections as needed to maintain the existing system. -
Answer c) Maintain the existing drainage system until the new system is functional.
d) Provide temporary connections as needed to maintain the existing system.
After flushing but before connecting a new main to the existing system, what test does an inspector need to verify before placing the main into service?
a)bacteriological testing
b)cover testing
c)deflection testing
d)pressure testing - Answer d) pressure testing
Which three types of inspections are completed for sign structures? (Choose three).
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller Loyimproved. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $8.99. You're not tied to anything after your purchase.