PJM Test Prep | 200 Questions with 100% Correct Answers | Verified | Latest Update 2024
PJM Test Prep | 200 Questions with 100% Correct Answers | Verified | Latest Update 2024 WHEN A BA IS UNDERGENERATING, IT MEANS? ANS-TOTAL GENERATION THE TOTAL LOAD REACTIVE RESERVE CHECK PROVIDES A SNAPSHOT OF RESERVES ON THE SYSTEM. WHAT ARE THE 3 TYPES OF RESERVES? ANS-1. UNIT MVAR RESERVE = TOTAL LAGGING RESERVE OF ALL SYNCED UNITS 2. SVC'S TOTAL LAGGING RESERVE 3. CAPACTIORS OUT OF SVC, REACTORS IN SVC COUNTS EACH IROL'S Tv SHALL BE LESS THAN OR EQUAL TO __________ MINUTES. ANS-30 MINUTES AFTER IROL VIOLATION EXCEEDS _______ MINUTES, PJM ISSUES MANUAL LOAD DUMP WARNING. ANS-5 MINUTES HOW LONG AFTER IROL VIOLATION WILL PJM ISSUE MANUAL LOAD DUMP WARNING? ANS-5 MINUTES AFTER IROL VIOLATION EXCEEDS _______ MINUTES, PJM ISSUES MANUAL LOAD DUMP ACTION. ANS-25 MINUTES HOW LONG AFTER IROL VIOLATION WILL PJM ISSUME MANUAL LOAD DUMP ACTION? ANS-25 MINUTES WHAT ARE THE THREE TYPES OF STABILITY? ANS-STEADY STATE TRANSIENT DYNAMIC STEADY STATE IS _______________AND IS SEEN IN SMALL, SLOW CHANGES. ANS-CONTROLLABLE TRANSIENT STATE AKA FIRST SWING IMMEDIATELY FOLLOWS _____________. ANS-SYSTEM DISTURBANCE THE ABILITY OF GENERATORS TO DAMPEN OSCILLATIONS CAUSED BY RELATIVELY MINOR DISTURBANCES THROUGH THE ACTIONS OF PROPERLY TUNED CONTROL SYSTEMS IS.... ANS-DYNAMIC STABILITY DYNAMIC STABILITY OCCURS OVER TIME AND IF NOT CORRECTED, WILL _______. ANS-GET WORSE THE A-B AREA OF THE D-CURVE WOULD INCUR OVERHEATING IN.... ANS-THE FIELDWINDING OF THE GENERATOR ROTOR THE B-C A
Written for
- Institution
- PJM
- Course
- PJM
Document information
- Uploaded on
- March 8, 2024
- Number of pages
- 19
- Written in
- 2023/2024
- Type
- Exam (elaborations)
- Contains
- Questions & answers
Subjects
-
when a ba is undergenerating it means
-
reactive reserve check provides a snapshot of rese
-
each irols tv shall be less than or equal to