100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
CSI – CDT EXAM 2024 QUESTIONS AND DETAILED ANSWERS WITH RATIONALE | 100% CORRECT ANSWERS GUARANTEED PASS $21.99   Add to cart

Exam (elaborations)

CSI – CDT EXAM 2024 QUESTIONS AND DETAILED ANSWERS WITH RATIONALE | 100% CORRECT ANSWERS GUARANTEED PASS

 1 view  0 purchase
  • Course
  • Institution

CSI – CDT EXAM 2024 QUESTIONS AND DETAILED ANSWERS WITH RATIONALE | 100% CORRECT ANSWERS GUARANTEED PASS

Preview 4 out of 45  pages

  • March 11, 2024
  • 45
  • 2023/2024
  • Exam (elaborations)
  • Questions & answers
avatar-seller
CSI – CDT EXAM 2024 QUESTIONS
AND DETAILED ANSWERS WITH
RATIONALE | 100% CORRECT
ANSWERS GUARANTEED PASS


Sheet keynote or reference keynote Correct Answer a notation
on a single drawing sheet

"A facility's "life cycle" includes all of the following EXCEPT:
a. Project conception
b. Financing
c. Construction
d. Facility management" Correct Answer 1. b - PRM 1.4 Life
cycle Stages: Conceptions, Delivery Method, Design,
Procurement, Construction,

What does CSI's UDS do ? what does it stand for ? Correct
Answer UDS uniform drawing system

CMa stands for... Correct Answer Construction Manager as
Advisor

"The objective of the competitive bidding process is:
a. To ensure that all qualified bidders may submit bids on public
work projects
b. To ensure that public works contracts are always awarded to
the lowest bidders
c. To ensure that the intent of the governing public laws is
maintained in the
awarding of contracts

,d. To ensure that the cost of the project is reasonable and
consistent with the
prevailing conditions in the building industry" Correct Answer 2.
d - PRM 3.4

What is included in PART 3 of SectionFormat? Correct Answer
PART 3- EXECUTION: describes field/site installation or
application, including preparatory actions and post-installation
cleaning and protection. Field/site-built assemblies and
field/site-manufactured products and systems are included.

"A unit price contract or contract portion is used when:

a. Extent of work cannot be fully determined or where actual
quantities cannot be accurately calculated.
b. Extent of work is known, but the owner desires a break-out
cost for portions of the work.
c. It is anticipated that bidders will not examine soil bearing
reports prior to submitting bid.
d. Bidding quantities of equipment.

Review: PDPG 7.1.6.2" Correct Answer "a. Extent of work
cannot be fully determined or where actual quantities cannot be
accurately calculated.

Use of unit prices, allowances and alternates should always be
limited to those items required for accurate bidding, in order to
keep bidding documents and processes as simple as possible."

"The contractual relationship governed by the Conditions of the
Contract is between:

a. Owner and contractor
b. Architect/engineer and contractor
c. Owner and Subcontractors
d. Owner, contractor, and architect/engineer

,Review: PDPG 5.5 and 11.3.9" Correct Answer "a. Owner and
contractor

The owner and the contractor are the parties to the construction
contract, hence they are subject to the Conditions of the
Contract. Yes, the duties of the architect are described in the
Conditions of the Contract, but they are governed by the
separate Owner/Architect or Owner/Engineer Agreement."

How long does a contractor required to execute corrections in
the Work after Substantial Completion? Correct Answer one
year

"Which of the following would be included in Available
Information?

a. Bid security requirements
b. Environmental Impact Statement
c. Time of completion to construct the project
d. Description of the Work

Review: PDPG 11.4.5" Correct Answer "b. Environmental
Impact Statement

Available Information is the place to provide reference
information such as this that doesn't belong in the contract. Bid
security info? In the Instructions for Procurement. Time of
Completion? It's contractual - where would you put it?
Description of Work? Name the Division 01 section where that
belongs."

"Instructions for Procurement:

a. Are used only on private projects
b. Frequently are standard industry forms
c. May include the geotechnical report as an attachment
d. Are binding upon the Contractor

, Review: PDPG 11.4.4
" Correct Answer "b. Frequently are standard industry forms

Both AIA and EJCDC offer standard printed Instructions to
Bidders forms. If necessary, a Supplementary Instructions to
Bidders can customize the Instructions to suit special project
conditions.

Did you notice? The PDPG uses the term ""Instructions for
Procurement"" as an umbrella term for both bid and negotiated
projects. MasterFormat lists both terms: Instructions for
Procurement, and the more specific documents Instructions to
Bidders or Instructions to Proposers."

"Marked-up or corrected contract drawings that indicate
changes incorporated in the Work are:

a. Contract forms
b. Closeout submittals
c. Record drawings
d. As-builts
e. Not required for private work

Review: PDPG 11.2.3.5" Correct Answer "c. Record drawings

These drawings incorporate all issued modifications and
significant field changes in scope. The term ""as-builts"" is
discouraged, as we are often unable to certify the accuracy of
actual installations and field-recorded information."

"Contractual clauses in the Conditions of the Contract:

a. Have priority over Division 01
b. Are superseded by Division 01
c. Are expanded upon by the provisions of Division 01
d. Are independent, and Division 01 provisions have no effect

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller Tutorkev. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $21.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

79064 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$21.99
  • (0)
  Add to cart