Based on the guide quantity of 100 CY on a bid document for rock excavation, a contractor bid a unit price of $20/CY. If the owner's representative determined that the contractor excavated 85 CY of rock during construction, how much will the contractor get paid? (a). $2000 (b). $1700 (c). $300 ...