Correct
1.00 points out of 1.00In resource allocation problems,
Select one:
a.The duration of a project is fixed, but resources are unlimited.
b.Resources are limited, but the duration of a project can be extended.
c.None of the items listed.
Your answer is correct.
The correct answer is: Resources are limited, but the duration of a project can be extended.
Question 2
Correct
1.00 points out of 1.00True or False: After resource allocation, a project's duration may be extended.
Select one:
True
Fals
e
The correct answer is 'True'.
Question 3
Correct
1.00 points out of 1.00In resource allocation problems, the project duration is often .
Select one:
a.Changed
b.Unchanged
Your answer is correct.
The correct answer is: ChangedCM 4100 CONSTRUCTION SCHEDULING AND CONTROL QUIZ 3 actual questions and answers 2024-2025
Louisiana State University The purpose of resource leveling is to
Select one:
Double up resource use in order to accelerate a project.
Smooth the use of resources.
Reduce resource use.
Your answer is correct.
The correct answer is: Smooth the use of resources.Question 4 Solve the resource scheduling problem with the series method. The resource limits are as follows (Chapter 6 Problem 2, page 96): 4C and 3L. After finish resource allocation, choose the correct answer. Please reference the diagram for questions 5-17 (Day 1 through Day 22)
\
DayActivity Resource Use
C L
Day 1
Day 2 to 3
Day 4
Day 5
Day 6
Day 7
Day 8
Day 9 to 12
Day 13 to14
Day 15
Day 16 to 17
Day 18 to 23
Day 24
First, fill out the chart for day 1.
DayActivity Resource Use
C L
Day 1
Select one:
a.
DayActivity Resource Use
C L
Day 1A 0 0
b.
DayActivity Resource Use
C L
Day 1B 1 0Question 5
Correct
1.00 points out of 1.00 c.
The correct answer is:DayActivity Resource Use
C L
Day 1C1 1
DayActivity Resource Use
C L
Day 1A 0 0