100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
CDT Exam Questions 100% Correct Answers Verified Latest 2024 Version $8.99   Add to cart

Exam (elaborations)

CDT Exam Questions 100% Correct Answers Verified Latest 2024 Version

 0 view  0 purchase
  • Course
  • Institution

CDT Exam Questions | 100% Correct Answers | Verified | Latest 2024 Version Select the entity which is generally assigned the following duties and responsibilities by the Conditions of the Contract: Protection of job site workers and stored materials. A - Architect/Engineer B - Owner C - Contr...

[Show more]

Preview 4 out of 65  pages

  • June 17, 2024
  • 65
  • 2023/2024
  • Exam (elaborations)
  • Questions & answers
avatar-seller
CDT Exam Questions | 100% Correct Answers |
Verified | Latest 2024 Version
Select the entity which is generally assigned the following duties and responsibilities by the Conditions of
the Contract: Protection of job site workers and stored materials.



A - Architect/Engineer

B - Owner

C - Contractor

D - Varies, as stated in the Supplementary Conditions

E - None of the above



Reference: PDPG 5.4.1.7 and PDPG 15.12.11; EJCDC C-700 Paras. 7.12 through 7.15; AIA A201 Sections
10.1, 10.2, and 10.4. Also see CCAPG 6.8; CCPG 9.14. - ✔✔Answer: C - Contractor. Safety provisions in
both EJCDC and AIA documents clearly make safety and protection of persons and property at the
construction Site the sole responsibility of the Contractor.



Select the entity which is generally assigned the following duties and responsibilities by the Conditions of
the Contract: Resolution of claims.



A - Owner

B - Contractor

C - Varies, as stated in the Supplementary Conditions

D - Initial Decision Maker



Reference: PDPG 15.15.3; AIA A201 Sections 1.1.8 and 15.2. Also see CCAPG Chapter 10 (particularly
CCAPG 10.3) - ✔✔Answer: D - Initial Decision Maker. The Initial Decision Maker is an entity that exists
only in AIA documents and is not used in EJCDC documents. In AIA documents, when an entity other
than the Architect is named as the Initial Decision Maker, said entity is identified in AIA A101 (Owner-
Contractor Agreement) Section 6.1. In actual practice with AIA documents, the Initial Decision Maker is
typically the Architect, but may be a third party considered to be neutral.

,select the entity which is generally assigned the following duties and responsibilities by the Conditions of
the Contract: Paying taxes for the Work.



A - Architect/Engineer

B - Owner

C - Contractor

D - Varies, as stated in the Supplementary Conditions

E - None of the above



Reference: EJCDC C-700 Para. 7.09; AIA A201 Section 3.6; PDPG 13.6.4.4 among others. Also see CCAPG
3.1.4. - ✔✔Answer: C - Contractor. Taxes are part of the cost of construction for which the Contractor is
responsible under the terms of the Contract Documents.



For public work, where public owners are often exempt from certain sales and ues taxes on materials
and equipment to be incorporated into the construction, typically an associated Supplementary
Conditions provision is necessary to properly indicate the statutory requirements for taxes, which can
vary significantly from state to state.



select the entity which is generally assigned the following duties and responsibilities by the Conditions of
the Contract: Right to stop work, if non-conforming Work fails to be corrected.



A - Architect/Engineer

B - Owner

C - Contractor

D - Varies, as stated in the Supplementary Conditions

E - None of the above



Reference: PDPG 15.9.5.1; EJCDC C-700 Para 14.06; AIA A201 Sections 2.4, 14.2 and 14.3. Also see
CCAPG 2.1; CCAPG 6.2.2; - ✔✔Answer: B - Owner. Standard contract documents such as EJCDC's and
AIA's reserve to the Owner sole right to stop or suspend the Work if the Work does not comply with the
Contract Documents. This right is solely the Owner's, and should never be assumed by or delegated to
the A/E (or a construction manager), because stopping the Work is an extreme action that almost always
results in a delay Claim from the Contractor for additional time and compensation. In EJCDC and AIA

,documents, the A/E does not have authority to stop or suspend the Work for non-conformance because
issuing such an order is tantamount to opening the Owner's checkbook and handing out money.



Which of the following is part of the construction documents but not part of the Contract Documents?



A - Procurement Forms

B - Agreement

C - Performance Bond

D - General Conditions

E - Addenda

F - Contract Modifications



Reference: PDPG 12.1 and PDPG 12.2; EJCDC C-700 Paras. 1.01.A.6 and 7; AIA A201 Section 1.1.1; and
"The Diagram". Also see CCAPG 1.3.1; CCAPG 8.2. Also see CSPG Chapter 9 - ✔✔Answer: A -
Procurement Forms (also known as the Bid Form and its supplements). The Procurement (Bidding)
Requirements, which include the advertisement or invitation to bid, instructions to bidders/proposers,
bid form, bid bond form (if any), qualifications statement (if any), and other bid form supplements (if
any), are required only for the Project's procurement (bidding/pricing) stage and therefore are not
typically considered to be "Contract Documents" (remember: "Contract Documents" exist only after the
parties have both signed the Owner-Contractor Agreement).



If you are still having trouble wrapping your mind around this, consider that the Procurement (Bidding)
requirements are necessary for, and apply only through, the procurement (bidding) stage—they address
matters only until the Owner-Contractor Agreement is signed and the Contract becomes effective.
Therefore, the Procurement (Bidding) Requirements are not necessary once the Contract is in effect.



46a: What is the "glue" that binds the Contract Documents together?

Reference: PDPG 11.1.2; PDPG 11.1.5. Also see CSPG Chapter 5, "Agreements". - ✔✔Answer: If you
answered "Agreement" you would not be entirely correct the correct answer is "signed Agreement" (see
PDPG Figure 11.1)



True or False: The Contracting Requirements include the performance bond.

, Reference: MasterFormat Division 00 (particularly 00 50 00 through 00 99 99); and "The Diagram". -
✔✔Answer: True. MasterFormat titles Division 00 as "Procurement and Contracting Requirements".
Procurement (Bidding) Requirements are those documents that pertain only to the procurement
(bidding) stage (e.g., advertisement or instructions to bidders, advertisement or invitation to bid,
instructions to bidders/proposers, bid form, bid bond form (if any), bidder qualifications statement (if
any), and other bid form supplements (if any). MasterFormat assigns these documents between 00 10 00
and 00 49 99.



The "Contracting Requirements" are the balance of Division 00 (per MasterFormat, documents between
00 50 00 and 00 99 99), including the Agreement form and its supplements (if any); project forms
(including the performance bond and payment bond); "conditions of the contract"; and
revisions/clarifications/modifications (including Addenda).



46c: Project-specific insurance requirements would usually be included in the ____ (fill in the blank).



Reference: PDPG 12.5. Also see CSPG Chapter 17 - ✔✔Answer: Supplementary Conditions. Project-
specific insurance requirements, such as the specific types of insurance and minimum coverage limits
required, are typically in the Supplementary Conditions. This is always the case with EJCDC documents,
and was the case with AIA documents until the 2017 edition of AIA A201 and AIA A101.



Both AIA A201 and EJCDC C-700 (General Conditions) contain basic insurance provisions. But for the
Owner to require that the Contractor furnish general liability insurance of not less than a certain
coverage amount, or to require that the Contractor furnish a certain type of railroad protective liability
insurance, such requirements would be in the Supplementary Conditions (EJCDC C-800, Supplementary
Conditions, includes model language, as does AIA A503—2007). However, with its 2017 documents, the
AIA extracted the specific requirements for certain types of insurance and created at new exhibit to AIA
A101 (Owner-Contractor Agreement). Thus, as of 2017, AIA includes Project-specific insurance
requirements in an exhibit to the Agreement.



Also see EJCDC C-700 Article 6 and EJCDC C-800, Guide to the Preparation of Supplementary Conditions,
provisions numbered SC-6.0x. Alternatively, see AIA A201 Section 11 and the insurance exhibit to AIA
A101—2017.



Note that EJCDC C-800 and AIA A101 are not materials required for the CDT exams, but are extremely
useful in the actual practice of preparing Supplementary Conditions. Arcadis US Water's Standard
Supplementary Conditions ("Document 00 73 01") is developed closely from EJCDC C-800.

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller hov. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $8.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

79064 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$8.99
  • (0)
  Add to cart