Which of these documents, might we find in the Project Manual but they are not contract documents?
A. The Agreement
B. Procurement Requirements
C. Addendum
D. Supplemental Conditions - ✔✔B
Before a model building code can become the building code for a jurisdiction, it has to be adopted by?
A. Authority Having Jurisdiction
B. State Government
C. Building Inspector
D. International Organization for Standardization - ✔✔A
The Construction Manager is hired by this entity?
A. General Contractor
B. Owner
C. A/E
D. Contract Administrator - ✔✔B
The parties to the Construction Agreement are?
A. General Contractor, Subcontractor, and Construction Manager
B. A/E, General Contractor, and Contract Administrator
C. Building Official and General Contractor
D. Owner, Contractor, and A/E - ✔✔D
The organization responsible for the General Conditions known as 201 are?
,A. DBIA
B. AGC
C. AIA
D. CSI - ✔✔C
When there is a dispute between the specifications and the drawings, what is the proper way to settle
the dispute?
A. The drawings have priority
B. The A/E should interpret
C. The specifications
D. Arbitration - ✔✔B
A subcontractor is obligated to the prime contractor in the same manner as the prime contractor is
obligated to the:
A. Architect
B. Owner
C. Material Supplier
D. Principal in Charge - ✔✔B
The requirements of the General Conditions can be modified or expanded to accommodate specific
project conditions, owner's requirements, or unusual aspects relating to the roles, rights, duties, and
responsibilities of the parties to the contract for construction, in this document:
A. Contract Modifications
B. Supplemental Conditions
C. Addendum
D. Consensus Documents - ✔✔B
Which of the following are not legal binding construction documents?
A. General Conditions
B. Specifications
, C. Preliminary Project Description
D. Addendum - ✔✔C
This document states that the Contractor shall review, approve, and submit to the Architect, shop
drawings, product data, samples, and similar submittals required by the contract documents. It also
states that the Architect will review and approve or take other appropriate action upon the Contractor's
submittals:
A. Construction Agreement
B. Field Order
C. General Requirements
D. AIA A201 - ✔✔D
Division 01 sections apply broadly to the execution of the work of all the other sections of the
specifications. In addition, they expand on certain administrative and procedural provisions of the:
A. Drawings
B. Construction Agreement
C. Conditions of the Contract
D. Procurement Documents - ✔✔C
Defined as the written and graphic documents prepared or assembled by the A/E for communicating the
project design for construction and administering the construction contract:
A. Construction Documents
B. Plans
C. Procurement Documents
D. Conditions of the Contract - ✔✔A
Typically, Procurement Requirements should not include which of the following documents?
A. Instructions for Procurement
B. Available Information, including Resource Drawings
C. Procurement Forms and Supplements