A person who engages in a business or activity that involves construction new water wells must possess a license from the: -️️Oregon Water Resource Department (OWRD) True or False Prompt billing and prompt collections make for a healthier cash flow. -️️True Oregon OSHA consultants WILL ...

[Show more]

Preview 4 out of 54  pages

  • August 7, 2024
  • 54
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • Oregon Construction Contractor
  • Oregon Construction Contractor
avatar-seller
MikeHarris
Oregon Construction Contractors CCB Test-Questions with
Correct Answers/ Verified/ 100% Pass
A person who engages in a business or activity that involves construction new water wells must
possess a license from the: - ✔️✔️Oregon Water Resource Department (OWRD)



True or False

Prompt billing and prompt collections make for a healthier cash flow. - ✔️✔️True



Oregon OSHA consultants WILL NOT: - ✔️✔️Issue citations or propose penalties for violations of
OSHA standards.



1) Questions to answer when preparing your project schedule include all of these except:



- All of these are questions to ask

- What equipment will be needed?

- How long will each task take to complete?

- What type of crew will be needed to complete the activity? - ✔️✔️- All of these are questions to
ask

- What equipment will be needed?

- How long will each task take to complete?

- What type of crew will be needed to complete the activity?



For Notice of Right Lien purpose, a commercial improvement is defined as: - ✔️✔️A structure that
is not used or intended for use as a residential building



I am the residential original contractor and I provide labor and materials for the project. Who do I
need to give a notice of Right to Lien to? - ✔️✔️Mortgagee



A quantity survey is also referred to as a: - ✔️✔️Take Off



Tagout involves placing a warning tag: - ✔️✔️On an energy-isolation device

,Other than Take Off, other common construction estimate types include all, except: - ✔️✔️Ballpark
Estimates



True or False

An on-site of host employer is responsible for ensuring a safe place of employment for leased or
temporary workers. - ✔️✔️True



The state unemployment tax rate varies base on: - ✔️✔️The history of unemployment claims
against the employer.



Stop work order violations can result in: - ✔️✔️- Any of these could be the result of failure to
comply with a stop work order.

- Court action

- Permit or license revocation

- Civil penalties



The ___________________ gives an overview of the project, deadlines, and general requirements. -
✔️✔️Invitation to Bid



"Job Logic" refers to: - ✔️✔️The sequence of work



True or False

Self-employment taxes apply to all forms of business entities. - ✔️✔️False



- Money earned and money spent are accounted for in the year they are received or paid,
respectively. - ✔️✔️In the Cash Method



The Itemized Summary is the basis for: - ✔️✔️A complete and accurate estimate of project costs
and lists all major items of work in the order they are to be performed.



A major difference between the EIN and the BIN is: - ✔️✔️One is federal and one is state

,Poor construction and storage practices can result in _________________ inside the structure walls.
- ✔️✔️Molds and fungus



Builders now must use corrosion-resistance flashing in these specified locations, except: -
✔️✔️Surrounding all interior bedroom doors.



Compliance with environmental regulations can protect a contractor from:



- All of these are correct

- Private party lawsuits

- Criminal and civil penalties

- Liability claims - ✔️✔️- All of these are correct

- Private party lawsuits

- Criminal and civil penalties

- Liability claims



Using the Quantity Take-Off method for estimating, you begin by estimating the cost of
_________________ for each individual task. - ✔️✔️Labor and materials



Contractors must apply for permits through: - ✔️✔️Their local building department



A cost effective method for managing material costs and keeping inventory costs down is the: -
✔️✔️JIT - Just In Time



These are materials prohibited form open burning in Oregon except for: - ✔️✔️Unpainted and
untreated scrap wood



An owner-seller may comply with the Homebuyers Protection Act (HPA) by:



- Doing any of these

- Purchasing title insurance that does not exclude filed or unfiled claims of lien,

- Obtaining lien waivers or releases

, - Retaining at least 25% of the sales price in escrow - ✔️✔️- Doing any of these

- Purchasing title insurance that does not exclude filed or unfiled claims of lien,

- Obtaining lien waivers or releases

- Retaining at least 25% of the sales price in escrow



What are the possible consequences that a contractor may face if he or she fails to provide the
information to the Owner About Construction Liens when required?



- All of these are correct

- Contractor may be fined

- Contractor may lose lien rights

- Contractor may have CCB license suspended - ✔️✔️- All of these are correct

- Contractor may be fined

- Contractor may lose lien rights

- Contractor may have CCB license suspended



Withheld taxes are considered to be "_____________" funds that do not belong to the business and
cannot be used for any other purpose. - ✔️✔️Trust



The major purpose of the building exterior shell is to: - ✔️✔️Provide protection for the building at
its exterior boundaries and to enclose a suitable interior environment



A project manager can be involved in more than one construction project at the same time. -
✔️✔️True



The building exterior shell may consist of:



- All of these are part of the building exterior shell

- Only windows and doors

- Only exterior wall assemblies

- Only roof assemblies - ✔️✔️- All of these are part of the building exterior shell

- Only windows and doors

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller MikeHarris. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $12.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

77973 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$12.49
  • (0)
  Add to cart