What action does a signal person intend the operator to perform if he extends his arm at
shoulder height, makes a fist with his hand, and sticks his/her thumb up? - CORRECT
ANSWER Boom up
When hoisting personnel, within what percentage of level must a telescopic boom crane
be in order for the gross ratings in the load chart to remain valid? - CORRECT ANSWER
1%
The load line of the crane you're operating contacts an energized power line. There's no
sign of any other danger, such as fire. What should you do? - CORRECT ANSWER
Stay in the cab until the lines are de-energized
According to OSHA 1926.1413, how many randomly distributed broken wires in rotation-
resistant rope are cause for replacement of the rope? - CORRECT ANSWER 2 broken
wires in 6 rope diameters
What is the net capacity of a crane on main boom unless the manufacturer states
otherwise? - CORRECT ANSWER The capacity listed in the load chart minus the
weight of the rigging and all attachments
What may happen to a properly rigged load when lifted off the ground unless the
operator takes account of boom deflection? - CORRECT ANSWER It could swing out
away from the crane
What Standard Method hand signal is being illustrated? - CORRECT ANSWER Swing
, LATEST NCCCO EXAM 2024-2025 QUESTIONS
WITH 100% CORRECT ANSWERS
Who should an operator respond to a "stop" signal from? - CORRECT ANSWER
Anyone
Which area do truck cranes without a 5th outrigger generally have no lifting capacity
unless the manufacturer states otherwise? - CORRECT ANSWER The fron
What is the definition of "operating radius?" - CORRECT ANSWER The distance from
the center of rotation of the crane to the center of gravity of the load
What applies to the capacities below the bold line shown on a load chart? - CORRECT
ANSWER They are based on the stability of the crane
In which quadrant are rough terrain crane capacities generally greater? - CORRECT
ANSWER Over the front
According to federal requirements, under what conditions is it okay for a person to ride
the headache ball? - CORRECT ANSWER It is never okay
By what percentage do most manufacturers require a crane's load chart capacity to be
reduced by for duty cycle operations such as high-volume concrete placement? -
CORRECT ANSWER 20%.
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller ACELEARNERS. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $13.49. You're not tied to anything after your purchase.