In a Design/Build project, there is a contractual relationship established
between: Right Ans - The Owner and single party, Typically a Contractor
associated with an A/E
For the Public sector, Which method is normally followed for the award of a
contract? Right Ans - Competitive Bidding
The Construction Manager is normally hired by? Right Ans - The Owner
The form of contract usually most difficult to administer during construction
is: Right Ans - Multiple Prime Contracts
In the Single-Prime contract situation the Owner does not have a contractual
relationship with which of the following Right Ans - Sub-contractor
In which phase are the specifications produced? Right Ans - Design Phase -
Construction Documents
Whose responsibility is it to produce the shop drawings? Right Ans - The
Contractor
Which organizational system is used in the preliminary stages of a project?
Right Ans - UniFormat
Who developed the first formal UniFormat? Right Ans - The AIA and The
CSI
Whose responsibility is the maintenance of the revised UniFormat? Right
Ans - The CSC and The CSI
When is the CSI/CSC UniFormat used? Right Ans - In the planning stage of a
project
When is the MasterFormat used? Right Ans - When organization of detailed
construction is required on the basis of materials or methods
, How many Divisions are found within the MasterFormat System? Right Ans
- 49
What would be an example of data filing with the MasterFormat System?
Right Ans - Product literature,\Sweets Catalog,\SpecData
What information is found within Division 13 in the MasterFormat System?
Right Ans - Special Construction
What are the three parts of the SectionFormat? Right Ans - General,
Products and Execution
In what part of the SectionFormat is found information on submittals?
Right Ans - Part 1, General
The third part of the Three-Part Section Format is: Right Ans - Execution
Section 06220 Millwork would be considered a: Right Ans - Level three
section
The document recommended to organize preliminary construction
information into a standard order on the basis of elements or systems is:
Right Ans - UniFormat
The bidding requirements are: Right Ans - A part of the construction
documents, but not the contract documents, and \nA part of the project
manual
Bidding documents are: Right Ans - Defined as all the construction
documents issued to bidders before the signing of an owner contractor
agreement
EJCDC 1910-16 is a document which: Right Ans - Suggests the primary
location for specific information in the construction documents
The Bidding Requirements include: Right Ans - The instruction to bidders,
the invitation to bid and the bid form.
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller Studyhall. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $12.49. You're not tied to anything after your purchase.