The relative importance of time, cost and quality is determined by... - answer the project
sponsor
How would you best describe project management? - answer the application of
processes and methods to achieve the project objectives
The project context describes... - answer the environment within which a project is
undertaken
A communication management plan identifies the relevant information that should be
communicated to... - answer the project stakeholders
Project risk management is best described as... – answer minimizing threats and
maximizing opportunities
A project issue is... - answer a major problem that requires formal escalation
Scheduling can best be defined as the process used to determine... - answer overall
project duration
The Product Breakdown Structure (PBS)... - answer to define the hierarchy of
deliverables that are required to be produced on the project
A valid KPI could be... - answermilestone achievement
Who owns the Project Management Plan (PMP)? - answerthe Project Manager
A user... - answerthose intended to receive benefits or operate outputs
A responsibility of the project manager is... - answerto deliver the project objectives to
enable benefits to be realised
What is the definition of Leadership? - answerthe ability to align others towards a
common purpose
Quality is best defined as... - answerfitness for purpose of deliverables
The main outcome of risk identification, in a risk management process, is to... -
answeridentify and describe all risk that might occur on the project
The relative importance of time, cost and quality is determined by... - answer the project
sponsor
How would you best describe project management? - answer the application of
processes and methods to achieve the project objectives
The project context describes... - answer the environment within which a project is
undertaken
A communication management plan identifies the relevant information that should be
communicated to... - answer the project stakeholders
Project risk management is best described as... – answer minimizing threats and
maximizing opportunities
A project issue is... - answer a major problem that requires formal escalation
Scheduling can best be defined as the process used to determine... - answer overall
project duration
The Product Breakdown Structure (PBS)... - answer to define the hierarchy of
deliverables that are required to be produced on the project
A valid KPI could be... - answermilestone achievement
Who owns the Project Management Plan (PMP)? - answerthe Project Manager
A user... - answerthose intended to receive benefits or operate outputs
A responsibility of the project manager is... - answerto deliver the project objectives to
enable benefits to be realised
What is the definition of Leadership? - answerthe ability to align others towards a
common purpose
Quality is best defined as... - answerfitness for purpose of deliverables
The main outcome of risk identification, in a risk management process, is to... -
answeridentify and describe all risk that might occur on the project