100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
ARE 5.0 PJM QUESTIONS AND ANSWERS 2024 $17.49   Add to cart

Exam (elaborations)

ARE 5.0 PJM QUESTIONS AND ANSWERS 2024

 2 views  0 purchase
  • Course
  • Pjm
  • Institution
  • Pjm

Exam of 5 pages for the course Pjm at Pjm (ARE 5.0 PJM)

Preview 2 out of 5  pages

  • August 14, 2024
  • 5
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • Pjm
  • Pjm
avatar-seller
julianah420
ARE 5.0 PJM


Partnering - answerA method of managing a project where various stakeholders in the
project all participate in the decision making process

What should a PM consider when selecting its internal team? - answerThe type and
complexity of the project, the size of the project, staff availability, experience levels,
billing rates, personalities

What are the 2 methods of scheduling a project? - answerBar char or Gantt chart &
critical path

Most common methods of compensation - answerStipulated sum, cost plus fee,
percentage of construction cost, unit cost

Total working fee - answerThe fee available to pay people to do the job after subtracting
fees for profit, consultants, and other expenses

stipulated sum/fixed price - answerThe owner pays the architect a fixed sum for a
specific set of services, these do not include reimbursable expenses

Cost plus fee - answerThe architect is compensated for the actual expenses of doing
the job plus a reasonable fee for profit

Multiple of direct personnel expense approach - answerDirect salaries of employees is
determined and multiplied by a factor to account for normal and required personnel
expenses, that amount is increased by a multiplier that includes provisions for overhead
and profit

Hourly billing rate method - answerThe multiplier is built into the hourly rate

Percentage of construction cost - answerThe professional fee is a fixed p centaur of the
cost of construction

Unit cost method - answerFees are based on a definable unit, such as square footage,
for such work as tenant planning in a leasing building, or on a per-house basis in a large
residential projectq

Four basic types of schedules - answerCritical path method schedule, milestone charts,
bar charts or Gantt charts, wall schedule

, When is the milestone chart used? - answerShort duration projects with relatively few
tasks to track and fees under $35,000

What are general obligation bonds? - answerBonds issued by a city or state and backed
by general tax revenue and the issuer's credit

Addendum - answerA modification to the procurement documents issued for bid of
negotiation. Addenda can be issued any time before the owner-contractor agreement is
executed, but are typically issued until some predetermined time before the bid opening.

Allowance - answerAn amount of money or quantity of materials identified by bidders for
work that is not completely defined in the procurement documents

Bid alternate - answerA portion of the work defined in the procurement documents for
which separate pricing is to be identified in bidders' approach

Payment bond - answerLabor and materials payment bond, is an amount of money
guaranteeing that the contractor will pay subcontractors, vendors, and suppliers for their
work.

What does a payment bond protect the owner from? - answerPotential mechanic's liens
and construction delays

Performance bond - answerA guarantee by an entity which ensures that, should the
contractor default during construction, there are sufficient funds to complete the project.

Qualifications-based selection (QBS) - answerThe owner selects a contractor solely in
the basis of the contractors qualifications

Value-based selection (VBS) - answerThe owner selects a contractor based on the
weighted values of multiple criteria, including construction cost or fee and proposed
schedule, as well as qualifications-based criteria such as past experience on similar
projects and proposed personnel.

Stipulated sum - answerLump sum or fixed sum bid. The bid price is offered as a single-
number value that represents all the costs required to build the project.

Guaranteed maximum price (GMP) - answerThe cost of construction that the contractor
assures the client that the project will be built for

What is a type 1 RFI? - answerGraphic/ confirming RFI. The most straightforward type
of RFI would take approximately 1-2 labor hours or rework for a full-time equivalent
employee. This type of RFI receives a 2-hour point

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller julianah420. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $17.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

67096 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$17.49
  • (0)
  Add to cart