According to the IBC, the "blank" is to hire the special inspector. - CORRECT ANSWER
owner or owners agent. 2009 IBC Section 1704.1
According to the IBC, the "blank" is the responsible for the approval of a person's
qualifications to act as a special inspector. - CORRECT ANSWER code official. 2009
IBC, Section 1704.1
According to the IBC, discrepancy corrections are made known to the building official by:
- CORRECT ANSWER final report. 2009 IBC, Section1704.1.2
When is the code official to be made aware of a discrepancy found during a special
inspection? - CORRECT ANSWER If it is not corrected by the contractor. 2009 IBC,
Section 1704.1.2
According to the Model Program for Special Inspection, the special inspector is to
document work that is nonconforming: - CORRECT ANSWER In a written report -
Section II B 4 - Model Programs
According to the Model Program for Special Inspection, the special inspector is to
prepare written report of inspection: - CORRECT ANSWER After each inspection visit
- Section II B 5 - Model Programs
According to the Model Program for Special Inspection, which of the following items does
not need to be included in each inspection report? - CORRECT ANSWER Description
of discussions with the contractor - Section B 5 - Model Programs
,ICC BOLTING 2024-2025 QUESTIONS WITH
100% CORRECT ANSWER
According to the Specification for Structural Joints using high strength bolts, the nominal
diameter of standard bolt holes shall be how much larger than the nominal bolt
diameter? - CORRECT ANSWER 1/16 inch - Specification for Structural Joints Table
3.1
Discrepancies in the work shall be brought to the immediate attention of the "blank" for
corrective action. - CORRECT ANSWER the contractor - 2009 IBC, Section 1704.1.2.
The special inspector shall furnish inspection reports to the "blank" and to the "blank"? -
CORRECT ANSWER Building Official and Registered Design professional
The special inspector shall provide continuos inspection of: - CORRECT ANSWER
Single-pass fillet welds greater than 5/16 inch in size - 2099 IBC, Table 1704.3, Item 5.3
The special inspections required by this code are not required where the work is done on
the premise of a? - CORRECT ANSWER Approved fabricator - 2009 IBC, Section
1704.2.2
The special inspection of the steel fabrication process shall not be required where the
fabricator does not perform any? - CORRECT ANSWER heating operations - 2009
IBC, Section 1704.3, Exceptions # 1
, ICC BOLTING 2024-2025 QUESTIONS WITH
100% CORRECT ANSWER
According to the Specifications for Structural Steel Buildings, ASTM Standard "blank" is
to be used for the material test for steel sheets. - CORRECT ANSWER A568 -
Section A31, Specifications for Structural Steel Buildings
According to the Specifications for Structural Steel Buildings, the "blank" conducts the
material tests for identification of the structural steel. - CORRECT ANSWER
Fabricator or Testing Laboratory - Section A31, Specifications for Structural Steel
Buildings.
According to the Specifications for Structural Steel Buildings, which of the following steel
members are allowed to be unidentified steel? - CORRECT ANSWER Unimportant
members, where their physical properties and weldability would not affect the structure
strength - Section A31b, Specifications for Structural Steel Buildings
According to the Code of Standard Practice for Steel Buildings and Bridges, how is steel
of special material to be identified? - CORRECT ANSWER It is marked by the
supplier - Section 5.1.1, Code of Standard Practice for Steel Buildings and Bridges
According to the Code of Standard Practice for Steel Buildings and Bridges, how are
fabricators stock steel material identified? - CORRECT ANSWER Certified mill test
reports - Section 5.2.2 - Code of Standard Practice for Steel Buildings and Bridges
According to the Specification for Structural Steel Buildings, what ASTM Standard would
apply to a sample for structural steel pipe? - CORRECT ANSWER A53 - Section A31a
- Specification for Structural Steel Buildings
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller ACELEARNERS. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $13.49. You're not tied to anything after your purchase.