One of the first steps in the system acquisition process is to:
a. Defining project objectives and scope of analysis
b. Determine system goals
c. Screen the marketplace and review vendor profiles
d. Establish a project steering committee and appoint project manager - Establish a project steerin...
BTE 450 Exam 2 Questions and Answers
One of the first steps in the system acquisition process is to:
a. Defining project objectives and scope of analysis
b. Determine system goals
c. Screen the marketplace and review vendor profiles
d. Establish a project steering committee and appoint project manager - Establish a
project steering committee and appoint project manager
What is NOT an advantage to contracting with an Application Service Provider
(ASP) to host an EMR?
a. Rapid deployment
b. Fixed costs
c. Customization
d. 24/7 technical support - Customization
The ideal project steering committee consists of how many members?
a. 3-4
b. 5-6
c. 10-12
d. 20-25 - 5-6
The phase of the system development life cycle where all alternatives are
considered, a cost-benefit analysis is done, a system is selected, and vendor
negotiations are finalized is known as:
a. Planning and analysis
b. Design
BTE 450 Exam 2 Questions and Answers
,BTE 450 Exam 2 Questions and Answers
c. Implementation
d. Evaluation and support - Design
The four phases of the system development life cycle in sequential order are:
a. Planning and analysis, implementation, design, support and evaluation
b. Support and evaluation, implementation, planning and analysis, design
c. Design, implementation, planning and analysis, support and evaluation
d. Planning and analysis, design, implementation, support and evaluation -
Planning and analysis, design, implementation, support and evaluation
Once the project steering committee has been established, one of the first things it
should is to:
a. Define project goals
b. Determine system requirements
c. Develop an RFP
d. Hold vendor demonstrations - Define project goals
What is the final step of the system acquisition process where expectations are
outlined and performance requirements are determined with the vendor?
a. Vendor demonstrations
b. Vendor analysis
c. Contract negotiations
d. Site visits - Contract negotiations
8. The final summary report developed by the project steering committee should
include everything but?
a. Systems goals and criteria
BTE 450 Exam 2 Questions and Answers
, BTE 450 Exam 2 Questions and Answers
b. Cost-benefit analysis
c. Final recommendation and ranking of vendors
d. Project repository - Project repository
What is an example of a research organization that produces market analysis
reports listing and describing vendors that provide EHR systems?
a. HIMSS
b. AMIA
c. ONC
d. KLAS - KLAS
10. The system acquisition process consists of what two phases of the systems
development life cycle:
a. Planning and Analysis, Design
b. Implementation, Support and Evaluation
c. Support and Evaluation, Planning and Analysis
d. Design, Implementation - Planning and analysis, design
The primary focus of the planning and analysis phase is on the business problem or
the organization's strategy, independent of any technology that can or will be used.
- True
It is generally advisable to have two or three vendors in the final ranking and
recommendations made by the project steering committee: - True
An RFP might be used when the health care organization is considering only a
small group of vendors or products or when it is still in the exploratory phase. -
False
BTE 450 Exam 2 Questions and Answers
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller CleanA. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $13.49. You're not tied to anything after your purchase.