Construction Exam Set Questions
With Revised Correct Answers
The SWPPP implementation sequence may be modified? -
ANSWER After consulting with the project SWPPP designer
(CEC) and if required, the project owner and receiving written
approval.
A SWPPP site map will show all of the following? - ANSWER
Location of BMP's, Phasing & Sequence, Limits of
Disturbance
Which of the following information is to be posted at the
entrance to the site? - ANSWER Construction site notice,
permit authorization, location of SWPPP
Which of the following is not a beneficial use water? - ANSWER
Flushing water down a storm drain
, When installing and maintaining a check dam make sure...? -
ANSWER The low point (overflow) of the check dam is in the
middle of the channel
To reduce the possibility of undercutting in channels, you
should? - ANSWER Install filter fabric under rock & similar
materials placed within the storm water conveyance.
The good housekeeping section of the SWPPP must include? -
ANSWER Hazardous waster management, solid waste,
sanitary waste and disposal procedures.
Runoff controls include? - ANSWER Diversions, check dams,
slope drains
Which erosion control best management practice increases
water infiltration, dissipates rainfall energy, and slows overland
flow of storm water? - ANSWER Vegetation
The contractor has the most control over what erosion rate
factor? - ANSWER Groundcover