100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
Project Management a questions and answers verified 2024 $13.49   Add to cart

Exam (elaborations)

Project Management a questions and answers verified 2024

 6 views  0 purchase
  • Course
  • WGU C722
  • Institution
  • WGU C722

Project Management a questions and answers verified 2024

Preview 3 out of 16  pages

  • August 28, 2024
  • 16
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • WGU C722
  • WGU C722
avatar-seller
LEWISSHAWN55
Project Management - C722 (UNIT 6
Quiz)
What creates a baseline for measuring progress as well as a road map for
determining how to get the job done?




Resource leveling
Planning
Budgeting
Negotiation - correct answer ✔Planning


Correct! Planning creates a baseline for measuring progress as well as a road
map for determining how to get the job done.


The purpose of which of the following is to authorize the project and serve as
a contract document showing agreement by the key stakeholders?




Triple constraints
Project charter
Stakeholder management plans
Project scope - correct answer ✔Project charter


Correct! The purpose of the project charter is to authorize the project and
serve as a contract document showing agreement by the key stakeholders.

,All planning documents need to be periodically reviewed to ensure that the
contents are still valid. These documents are defined as what?




Living documents
Static documents
Critical paths
Milestones - correct answer ✔Living documents


Correct! All planning documents are living documents, which means they
need to be periodically reviewed and updated to ensure that the contents are
still valid.


Which of the following documents the customer's expectations about when the
project will be completed, how much the completed project will cost, and how
project results will be measured?




Project scope
Project sponsor
Scrum
Project budget - correct answer ✔Project scope


Correct! The project scope documents the customer's expectations about
when a project will be completed and how much the project will cost. It
becomes the standard by which project results will be measured.


The initial scope statement is prepared as part of the defining phase. During
which phase is the approved scope statement developed?

, Planning
Scope creep
Closing
Executing - correct answer ✔Planning


Correct! The initial scope statement is prepared as part of the defining phase
and the approved scope statement is developed as part of the planning
phase.


Which of the following is a characteristic, function, or capability that must be
present in the project's final outcome?




Project requirement
Milestone
Critical path
Requirements Traceability Matrix - correct answer ✔Project requirement


Correct! A project requirement is a characteristic, function, or capability that
must be present in the project's final outcome


Which of the following is a verifiable outcome of work activities or the overall
project?




Critical path

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller LEWISSHAWN55. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $13.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

79271 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$13.49
  • (0)
  Add to cart