Which of the following statements is NOT true?
a. The government encourages the maximum practicable commercial use of inventions made
under government contracts.
b. The government recognizes rights in data developed at private expense, and limits its demands
for delivery of that data.
c. The government requires that contractors obtain permission from copyright owners before
including copyrighted works, owned by others, in data to be delivered to the government.
d. Generally, the government will refuse to award a contract on the grounds that the prospective
contractor may infringe a patent. - answer✔✔d. Generally, the government will refuse to award a
contract on the grounds that the prospective contractor may infringe a patent.
FAR 27.102
Performance and payment bonds are required or may be required for
a. construction contracts and services and supply contracts exceeding $2,000.
b. construction contracts exceeding $150,000.
c. any contract for services,
d. construction contracts exceeding $150,000 and services and supply contracts exceeding the
SAT when necessary to protect the governments interests. - answer✔✔d. construction contracts
exceeding $150,000 and services and supply contracts exceeding the SAT when necessary to
protect the governments interests.
FAR 28.102-1(a), 28.103-1(a), 28.103-2(a)
Cost Accounting Standards Board rules and regulations apply to
a. negotiated contracts and subcontracts.
b. sealed bid contracts.
c. contracts with small business concerns.
d. bridge contracts. - answer✔✔a. negotiated contracts and subcontracts.
FAR 30.000
The head of the agency may waive the applicability of Cost Accounting Standards (CAS) for a
particular contract or subcontract when one of these conditions exists:
a. The contract or subcontract is less than $50 million, primarily engaged in the sale of
commercial items, and has no contracts/subcontracts subject to CAS.
b. The contract or subcontract is less than $15 million, primarily engaged in the sale of
commercial items, and has no contracts/subcontracts subject to CAS.
c. The contract or subcontract is less than $7.5 million, primarily engaged in the sale of
commercial items.
d. The contract or subcontract is less than $5 million, primarily engaged in the sale of
commercial items, and has no contracts/subcontracts subject to CAS. - answer✔✔b. The contract
or subcontract is less than $15 million, primarily engaged in the sale of commercial items, and
has no contracts/subcontracts subject to CAS.
FAR 30.201-5
Which of the following statements about advance agreements is NOT true?
a. Advance agreements may only be negotiated with a particular contractor for a single contract.
b. Advance agreements may be negotiated either before or during a contract.
c. The agreement must be in writing.
d. The agreements must be incorporated into applicable current and future contracts. -
answer✔✔a. Advance agreements may only be negotiated with a particular contractor for a
single contract.
FAR 31.109
A cost is reasonable if, in its nature and amount, it does not exceed that which would be
a. incurred by a prudent person in the conduct of competitive business.
b. accrued by a prudent person in the conduct of competitive business.
c. determined to be allowable by the CO.
d. determined to be allocable by the CO. - answer✔✔a. incurred by a prudent person in the
conduct of competitive business.
FAR 31.201-3
What definition best describes alternative dispute resolution?
a. Procedures used to resolve issues in controversy.
b. Procedures voluntarily used to resolve issues in controversy.
c. Procedures used for asserting and resolving claims.
d. Procedures voluntarily used for asserting and resolving claims. - answer✔✔b. Procedures
voluntarily used to resolve issues in controversy.
FAR 33.214
The government's policy is to try to resolve all contractual issues in controversy by
a. mutual agreement at the CO's level.
b. bilateral agreement at the CO's level.
c. mutual agreement at a level above the CO.
d. unilateral agreement at the CO's level. - answer✔✔a. mutual agreement at the CO's level.
FAR 33.204
After receiving the GAO's written notice that a protest has been filed, an agency must give notice
a. of the protest to the contractor or all parties who appear to have a reasonable prospect of
receiving an award.
b. of the protest only to the prime contractor performing the work.
c. of the protest to all parties who appear to have a reasonable prospect of receiving award and
begin compiling the information necessary to report to the GAO.
d. through a government-wide point of entry (GPE). - answer✔✔a. of the protest to the
contractor or all parties who appear to have a reasonable prospect of receiving an award.
FAR 33.104
Does a $75,000 claim resulting from a reduction of $350,000 and an increase of $275,000
require certification?
a. No, because the claimed amount is less than $100,000.
b. Yes, because the aggregate value of the claim exceeds $100,000.
c. No, because the claimed amount is less than $500,000.
d. Yes, because the aggregate value of the claim exceeds $500,000. - answer✔✔b. Yes, because
the aggregate value of the claim exceeds $100,000.
FAR 33.207(d)
Protests may be filed with
a. either the agency or the GAO.
b. the agency, the GAO, or the U.S. Court of Claims.
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller Thebright. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $12.49. You're not tied to anything after your purchase.