100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
APM PMQ ACTUAL EXAM NEWEST VERSION REVISED 90 QUESTION AND CORRECT ANSWER FROM VERIFIED SOURCES RATED A GRADE. $16.99   Add to cart

Exam (elaborations)

APM PMQ ACTUAL EXAM NEWEST VERSION REVISED 90 QUESTION AND CORRECT ANSWER FROM VERIFIED SOURCES RATED A GRADE.

 7 views  0 purchase
  • Course
  • APM PMQ
  • Institution
  • APM PMQ

APM PMQ ACTUAL EXAM NEWEST VERSION REVISED 90 QUESTION AND CORRECT ANSWER FROM VERIFIED SOURCES RATED A GRADE.

Preview 3 out of 21  pages

  • August 28, 2024
  • 21
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • APM PMQ
  • APM PMQ
avatar-seller
teachme2expert
APM PMQ EXAM ACTUAL EXAM NEWEST VERSION 2024-
2025 REVISED 90 QUESTION AND CORRECT ANSWER FROM
VERIFIED SOURCES RATED A GRADE.


What are the steps of the configuration management process? ✔✔CORRECT
ANSWER✔✔Planning
Identification
Control
Status Accounting
Audit


What are 2 types of breakdown structure? ✔✔CORRECT ANSWER✔✔Work
Breakdown Structure (WBS)
Product Breakdown Structure (PBS)


What is a Work Breakdown Structure (WBS)? ✔✔CORRECT ANSWER✔✔a
comprehensive list of all activities needed to complete a project.


What is a Product Breakdown Structure (PBS)? ✔✔CORRECT
ANSWER✔✔This focuses on the deliverables that are needed to deliver the
project. This can be broken down further into tasks within a WBS.


What are 5 types of report? ✔✔CORRECT ANSWER✔✔Progress
Quality

,Risk
Finance
Audit


What are 3 types of investment appraisal? ✔✔CORRECT ANSWER✔✔Net
present value (NPV)
Payback
Internal Rate of Return (IRR)


What are the steps of the stakeholder management process? ✔✔CORRECT
ANSWER✔✔Identify
Assess
Develop
Engage


What should a business case include? ✔✔CORRECT ANSWER✔✔B -
Background
O - Options
B- Benefits
CA - Commercial Aspects
R - Risks
T - Timescales


What are the 5 aspects of the PRAM? ✔✔CORRECT ANSWER✔✔Initiate

, Identify
Assess
Plan responses
Implement responses


What are the 5 phases in the extended project life cycle? ✔✔CORRECT
ANSWER✔✔Concept
Definition
Development
Handover and Closure
Operations


Who are potential stakeholders within a project? ✔✔CORRECT
ANSWER✔✔Project Sponsor
Project Team
Users
Suppliers
Customers
Senior Management


What are the 5 steps within the information management process?
✔✔CORRECT ANSWER✔✔Collection
Storage
Dissemination

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller teachme2expert. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $16.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

78998 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$16.99
  • (0)
  Add to cart