100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
PMP Exam Question and Answers (Latest Update) $15.99   Add to cart

Exam (elaborations)

PMP Exam Question and Answers (Latest Update)

 5 views  0 purchase
  • Course
  • PMP
  • Institution
  • PMP

PMP Exam Question and Answers (Latest Update) Earned Value (EV) Correct Answer-The measure of work performed expressed in terms of the budget authorized for that work. BAC x % Work Completed Planned Value (PV) Correct Answer-The portion of the approved total cost estimate planned to be spe...

[Show more]

Preview 4 out of 60  pages

  • August 29, 2024
  • 60
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • PMP
  • PMP
avatar-seller
KarmaScores
PMP Exam Question and Answers (Latest
Update)
Earned Value (EV) Correct Answer-The measure of work performed
expressed in terms of the budget authorized for that work. BAC x % Work
Completed


Planned Value (PV) Correct Answer-The portion of the approved total cost
estimate planned to be spent on an activity during a given period. Planned %
Complete x BAC


Actual Cost (AC) Correct Answer-The realized cost incurred for the work
performed on an activity during a specific time period.


Budget at Completion (BAC) Correct Answer-The sum of all budgets
established for the work to be performed.


Estimate to Complete (ETC) Correct Answer-The expected cost to finish all the
remaining project work. EAC - AC


Estimate at Completion (EAC) Correct Answer-The expected total cost of
completing all work expressed as the sum of the actual cost to date and the
estimate to complete. BAC / CPI


Cost Performance Index (CPI) Correct Answer-A measure of the cost
efficiency of budgeted resources expressed as the ratio of earned value to actual
cost. EV / AC


Schedule Performance Index (SPI) Correct Answer-A measure of schedule
efficiency expressed as the ratio of earned value to planned value. EV / PV

, PMP Exam Question and Answers (Latest
Update)

To-Complete Performance Index (TCPI) Correct Answer-A measure of the cost
performance that is required to be achieved with the remaining resources in
order to meet a specified management goal, expressed as the ratio of the cost to
finish the outstanding work to the remaining budget. (BAC - EV) / (BAC - AC)


Cost Variance (CV) Correct Answer-EV - AC
Negative is over budget; positive is under budget


Schedule Variance (SV) Correct Answer-EV - PV
Negative is behind schedule; positive is ahead of schedule


Variance at Completion (VAC) Correct Answer-A projection of the amount of
budget deficit or surplus, expressed as the difference between the budget at
completion and the estimate at completion. BAC - EAC


Economic Value Added (EVA) Correct Answer-Net operating profit after taxes
minus (capital x cost of capital); a measure of the economic value of an
investment or project


Future Value (FV) Correct Answer-the value of future cash flows discounted
at the appropriate discount rate FV = PV(1+r)^n


Return on Invested Capital (ROIC) Correct Answer-Net income after tax /
Invested Tax (smaller is better)

, PMP Exam Question and Answers (Latest
Update)
Order of Magnitude Estimate Correct Answer-A high-level estimate of the
time and cost of a project based on the actual cost and duration of a similar
project. -50% to +100%


Conceptual Estimate Correct Answer-a cost estimate based on very little
design information and using gross unit pricing to determine the project cost. -
30% to +50%


Preliminary Estimate Correct Answer--20% to +30% estimate range


Definitive Estimate Correct Answer--15% to +20% estimate range


Control Estimate Correct Answer--10% to +15% estimate range


Delphi Technique Correct Answer-A decision-making technique in which
group members do not meet face-to-face but respond in writing to questions
posed by the group leader. Prevents biasing opinions and groupthink.


Nominal Group Technique Correct Answer-Brainstormed ideas are voted
upon and sorted by priority


Scope Baseline Correct Answer-The approved version of a scope statement,
work breakdown structure (WBS), and its associated WBS dictionary, that can be
changed only through formal change control procedures and is used as a basis
for comparison.

, PMP Exam Question and Answers (Latest
Update)
Baseline Correct Answer-The original plan plus all approved changes (scope,
schedule, cost)


Functional Organization Correct Answer-Departmentalization around
specialized activities such as production, marketing, and human resources.


Projectized Organization Correct Answer-Any organizational structure in
which the project manager has full authority to assign priorities, apply
resources, and direct the work of persons assigned to the project.


Matrix Organization Correct Answer-An organization in which specialists
from different parts of the organization are brought together to work on specific
projects but still remain part of a line-and-staff structure. Strong, Balanced, and
Weak, where in strong PM has power.


Project Scope Statement Correct Answer-The description of the project
scope, major deliverables, assumptions, and constraints. Includes product scope
description, acceptance criteria and project exclusions.


Work Breakdown Structure (WBS) Correct Answer-A hierarchical
decomposition of the total scope of work to be carried out by the project team
to accomplish the project objectives and create the required deliverables.


Lead Correct Answer-Starting an activity prior to the finish of the preceding
activity

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller KarmaScores. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $15.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

73091 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$15.99
  • (0)
  Add to cart