Unlock the secrets to mastering resource management with our comprehensive quiz guide! This resource management quiz covers essential terms and concepts like resource loading, smoothing, and optimization, ensuring you grasp critical strategies for effective project and business management. Perfect ...
BUSINESS MANAGEMENT – APM PMQ COMPETENCE TEST 2024 SERIES 11
RESOURCE MANAGEMENT QUIZ
NOTE: This is part 11 of a complete series of APM (Association for Project Management) PMQ
(Project Management Qualification) as of September 2024 all you need for your exam preps
Circle the letter of the Definition that corresponds to the displayed Term.
1
Question: Resource loading
a) An approach used during resource optimisation that delays activities such that the resource level is
kept below specified limits. Also known as resource limited scheduling.
b) A method of resource optimisation that uses float or resource adjustment so that peaks or troughs of
resource usage are smoothed out, so avoiding extension of the duration where possible. Also known as
time limited scheduling.
c) The amount of resources of each kind devoted to a specific activity in a particular time period.
d) The acquisition and deployment of the internal and external resources required to deliver the project,
programme or portfolio.
Correct Answer: The amount of resources of each kind devoted to a specific activity in a particular
time period.
Explanation: Resource loading refers to the specific allocation of resources to tasks during a given
time period, indicating how resources are distributed across activities.
2
Question: Resources
a) An approach used during resource optimisation that delays activities such that the resource level is
kept below specified limits. Also known as resource limited scheduling.
b) A method of resource optimisation that uses float or resource adjustment so that peaks or troughs of
resource usage are smoothed out, so avoiding extension of the duration where possible. Also known as
time limited scheduling.
c) All the labour and non-labour items required to undertake the scope of work to the required quality.
d) The amount of resources of each kind devoted to a specific activity in a particular time period.
Correct Answer: All the labour and non-labour items required to undertake the scope of work to the
required quality.
Explanation: Resources encompass all elements needed to complete a project, including both human
and non-human resources, necessary for achieving the desired outcomes.
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller GoldenChapter. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $5.49. You're not tied to anything after your purchase.