100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
BUSINESS MANAGEMENT – APM PMQ COMPETENCE TEST 2024 SERIES 13 (BUDGETING COST CONTROL QUIZ) $5.49   Add to cart

Exam (elaborations)

BUSINESS MANAGEMENT – APM PMQ COMPETENCE TEST 2024 SERIES 13 (BUDGETING COST CONTROL QUIZ)

 7 views  0 purchase
  • Course
  • Business Management
  • Institution
  • Business Management

Unlock your mastery of budgeting and cost control with our expertly crafted quiz! Perfect for business and management students, this comprehensive quiz delves into key concepts such as the Organisational Breakdown Structure (OBS), Budget at Completion (BAC), and Earned Value Management (EVM). With ...

[Show more]

Preview 1 out of 4  pages

  • August 31, 2024
  • 4
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • Business Management
  • Business Management
avatar-seller
GoldenChapter
Business Management

BUSINESS MANAGEMENT – APM PMQ COMPETENCE TEST 2024 SERIES 13

BUDGETING COST CONTROL QUIZ

NOTE: This is part 13 of a complete series of APM (Association for Project Management) PMQ
(Project Management Qualification) as of September 2024 all you need for your exam preps

Circle the letter of the Definition that corresponds to the displayed Term.
1
Question: Organisational breakdown structure (OBS)

a) A hierarchical way in which the organisation may be divided into management levels and groups, for
planning and control purposes.
b) The sum total of the time-phased budgets.
c) A project control process based on an approach to planning, cost collection and performance
measurement. It facilitates the integration of project scope, time and cost objectives and the
establishment of a baseline plan of performance measurement.
d) The authorised budget assigned to the scheduled work to be completed. Also referred to as the
budgeted cost of work scheduled (BCWS).

Correct Answer: A

Explanation: The Organisational Breakdown Structure (OBS) is a hierarchical representation of how
an organization is divided into management levels and groups for effective planning and control
purposes.



2
Question: BAC (Budget at completion)

a) A project control process based on an approach to planning, cost collection and performance
measurement. It facilitates the integration of project scope, time and cost objectives and the
establishment of a baseline plan of performance measurement.
b) The sum total of the time-phased budgets.
c) A measure of progress that expresses costs committed and work achieved in the same units.
d) The hierarchical breakdown of a project into cost elements.

Correct Answer: B

Explanation: The Budget at Completion (BAC) is the sum total of all time-phased budgets for a
project, representing the total budgeted cost of the project.




© Strategic Business Management Scholars -2024

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller GoldenChapter. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $5.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

75632 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$5.49
  • (0)
  Add to cart