AIC Exam Chapter 3 Management Concepts Questions & Answers 2024
Which of the following is a fundamental element of a contract?
A.exchange of money
B. revised scope of work
C. time extension
D. mutual acceptance - ANSWERSD. mutual acceptance
Which of the following contract types is gen...
Which of the following is a fundamental element of a contract?
A.exchange of money
B. revised scope of work
C. time extension
D. mutual acceptance - ANSWERSD. mutual acceptance
Which of the following contract types is generally considered to have the most risk for the contractor?
A. lump sum
B. unit price
C. cost plus
D. cost plus with GMP - ANSWERSA. lump sum
Which of the following contract types is best used if the scope is well defined but not the quantities of
material?
A. lump sum
B. unit price
C. cost plus
D. cost plus with GMP - ANSWERSB. unit price
In which delivery method is the construction administrator most like a consultant?
A. lump sum
B. CM agency
C. CM at risk
D. integrated project delivery - ANSWERSB. CM agency
, Which statement is true about the design- build delivery method from the owner's perspective?
A. Design is complete when contractor is
hired.
B. Fast tracking is difficult with this delivery
method.
C. There is a single source of fault for
building system failures.
D. Design Build firms are rarely temporary
joint ventures. - ANSWERSC. There is a single source of fault for
building system failures.
Which delivery method has the most risk for the contractor?
A. design-bid-build
B. design-build
C. CM at risk
D. integrated project delivery - ANSWERSB. design-build
Which of the following is a major difference between a CM agency and a CM at risk?
A. manages construction on the owner's
behalf
B. has a contract with the designer
C. provides a lump sum price for
construction services
D. caps the construction costs the owner is
required to pay - ANSWERSD. caps the construction costs the owner is
required to pay
Under which legal structure are the least total taxes paid for the goods and services provided by the
company?
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller Bensuda. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $7.99. You're not tied to anything after your purchase.