PMP Exam Prep UPDATED Exam
Questions and CORRECT Answers
Schedule Development/Project Time Management - Correct Answer- Analyzing activity
sequences, durations, resource requirements, and schedule constraints to create the project
schedule
Activity Duration Estimating/Project Time Management - Correct Answer- Estimating the
number of work periods that will be needed to complete individual schedule activities
Activity Resource Estimating/Project Time Management - Correct Answer- Estimating the
type and quantities of resources required to perform each schedule activity
Activity Sequencing/Project Time Management - Correct Answer- Identifying and
documenting dependencies among schedule activities
Manage Stakeholders/Project Communications Management - Correct Answer- Managing
communications to satisfy the requirements of, and resolve issues with, project stakeholders
What process group does 'Perform Quantitative Risk Analysis' belong to? - Correct Answer-
Planning
What process group does 'Verify Scope' belong to? - Correct Answer- Monitoring and
Controlling
What process group does 'Manage Stakeholder Expectations' belong to? - Correct Answer-
Executing
What process group does 'Perform Quality Control' belong to? - Correct Answer- Monitoring
and Controlling
What process group does 'Collect Requirements' belong to? - Correct Answer- Planning
, Contract Administration/Project Procurement Management - Correct Answer- Managing the
contract and the relationship between the buyer and the seller, reviewing and documenting
how a seller is performing or has performed to establish required corrective actions and
provide basis for future relationship with seller
What process group does 'Adminsiter Procurements' belong to? - Correct Answer-
Monitoring and Controlling
Risk REsponse Planning/Project Risk Management - Correct Answer- Developing Options
and actions to enhance opportunities and to reduce threats to projcect objectives
Activity Definition/Project Time Management - Correct Answer- Identifying the specific
schedule activities that need to be performed to produce the various project deliverables
What process group does 'Control Scope' belong to? - Correct Answer- Monitoring and
Controlling
Plan Contracting/Project Procurement Management - Correct Answer- Dcoumenting
products, services and results requirements and identifying potential sellers
Select Sellers/Project Procurement Management - Correct Answer- Reviewing offers,
choosing from among potential sellers, and negotiating a written contract with a seller
Request Seller Responses/Project Procurement Management - Correct Answer- Obtaining
information, quotations, bids, offers or proposals as appropriate
EAC forecast for ETC at BUDGETED RATE - Correct Answer- EAC=AC+BAC-EV
EAC forecast for ETC at PRESENT CPI - Correct Answer- EAC=BAC/(cumulative CPI)
EAC forecast for ETC at both CPI & SPI factors - Correct Answer- EAC=AC+((BAC-
EV)/(Cumulative CPI x Cumulative SPI))
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller MGRADES. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $7.99. You're not tied to anything after your purchase.