BSCI 4610 Test 1 - Scheduling Planning Scheduling Executing - Answer- What are the overall goals of a typical construction Project? Difference between planning and scheduling - Answer- -Planning Identifies activities -Scheduling determines logic and duration for those activities Reaso...

[Show more]

Preview 1 out of 4  pages

  • September 9, 2024
  • 4
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • BSCI 4610 1 - Scheduling
  • BSCI 4610 1 - Scheduling
avatar-seller
Freshy
BSCI 4610 Test 1 - Scheduling
Planning
Scheduling
Executing - Answer- What are the overall goals of a typical construction Project?

Difference between planning and scheduling - Answer- -Planning Identifies activities
-Scheduling determines logic and duration for those activities

Reasons to Schedule - Answer- Coordinate and Communicate Expectations
Incorporate Key Procurement Issues
Track Progress
Forecasting - Time and Labor
Historical Data - For Current Projects/Future Projects

Terms on a Schedule - Answer- WBS (Work Breakdown Structure)
- Can have Sub WBS's (not required though)
Activities

Columns on a Schedule - Answer- Activity ID
Activity Description
Original Duration
Remaining Duration
Total Float
% Complete
Start Date
Finish Date

Items on a Gant Chart - Answer- WBS
Sub WBS
Logic Line
Activity Description
Data Date
Bar Length (Duration - in WORKING DAYS)

Finish to Start - Answer- Activity "B" can't begin until Activity "A" is completed

Start to Start - Answer- Activity "A" and Activity "B" begin on the same day. The
durations DO NOT need to be the same.

Finish to Finish - Answer- Activity "A" and Activity "B" finish on the same day.

Start to Finish - Answer- Activity "B" can't finish until Activity "A" has started. Activity
"A" is often a Milestone or "Level of Effort"

Lag - Answer- A delay to an activity beginning

Example of Lag - Answer- Activity A: Paint Final Coat

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller Freshy. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $10.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

73091 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$10.49
  • (0)
  Add to cart