construction jobsite management 4th edition by wil
construction jobsite management 4th edition
construction jobsite management
Connected book
Book Title:
Author(s):
Edition:
ISBN:
Edition:
More summaries for
Construction Jobsite Management 4th Edition By William R. Mincks; Hal Johnston Solutions Manual
Solutions Manual for Construction Jobsite Management 4th Edition by William R. Mincks; Hal Johnston Chapter 1-18 Complete Guide
Solutions Manual for Construction Jobsite Management 4th Edition by William R. Mincks; Hal Johnston Chapter 1-18 Complete Guide
All for this textbook (5)
Written for
Construction Jobsite Management 4th Edition By Wil
All documents for this subject (3)
Seller
Follow
kushboopatel6867
Reviews received
Content preview
Construction Jobsite Management 4th Edition By
William R. Mincks; Hal Johnston Solutions Manual
Which of the following is like a receipt that is given to the owner telling him that
everything regarding the financial aspect of the project has been settled ? - ANSWER:
affidavit of payment
Consent of surety is executed by : - ANSWER: the bonding company
Which type of drawing is completed by the manufacturer or a representative of the
manufacturer - ANSWER: Shop
The term for showing how quickly aspects of the project are being completed by
laborers is called - ANSWER: labor productivity
A(n) _____ will show the important information regarding each chemical on the
project site and is required by osha to be available - ANSWER: Material Safety Data
Sheet (MSDS)
Most contracts required the contractor to prepare record drawings or "as-built"
drawings during the project. This process entails recording ___,____&___ - ANSWER:
actual dimensions, location of utilities and changes in drawings
The main purposes of using a subcontractor - ANSWER: specialized labor for
particular construction task , lower cost for subcontract work and reduced risk for
the contractor
A list of all the cost associated within each aspect of the project and how the
progress payments are figured is an - ANSWER: Schedule of Values
A(n) will track progression of where delays are - ANSWER: submittal log
The supplementary conditions to the contract are additional provisions or
modifications to: - ANSWER: The General Conditions of the contract
When there is an issue that involves claims over____, arbitration is used - ANSWER:
1,000,000
A describe action that leads to accomplishing the project which usually includes
completing the project within the scope of time identified in the contract and within
the budget is a(n) - ANSWER: objective
Submittal of ____,_____ and _____ in a complete and timely fashion is essential for
the smooth execution of the construction contract. - ANSWER: product data, shop
drawings and samples
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller kushboopatel6867. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $17.99. You're not tied to anything after your purchase.