QUESTION: Develop Project Charter Inputs - ANSWER-Business documents, Agreements,
Enterprise Enviro. factors, and Org. process assets
QUESTION: Develop Project Charter Tools & Techniques x - ANSWER-Expert judgement, data
gathering, interpersonal & team skills, and meetings. x
QUESTION: Develop Project Charter Outputs - ANSWER-Project Charter, Assumption log
QUESTION: Develop PM Plan Inputs - ANSWER-Proj. charter, outputs from other processes,
Enterprise enviro. factors, and Org. process assets
QUESTION: Develop PM Plan Tool & Techniques - ANSWER-Expert judgement, data gathering,
interpersonal and team skills, and meetings
QUESTION: Develop PM Plan Outputs - ANSWER-PM Plan
QUESTION: Direct and Manage Project Work, Inputs - ANSWER-PM plan, proj. docs, approved
change requests, enterprise enviro. factors, and org. process assets
1
,Page 2 of 114
QUESTION: Direct and Manage Project Work, Tools & Techniques - ANSWER-Expert judgement,
PMIS, and meetings
QUESTION: Direct and Manage Project Work, Outputs - ANSWER-Deliverables, work
performance data, issue log, change requests, PM plan updates, proj. docs. updates, and org.
process assets updates
QUESTION: Manage Project Knowledge, Inputs - ANSWER-PM plan, proj. docs., deliverables,
enterprise enviro. factors, and org. process assets
QUESTION: Manage Project Knowledge, Tools & Techniques - ANSWER-Expert judgement,
knowledge management, information management, interpersonal & team skills
QUESTION: Manage Project Knowledge, Outputs - ANSWER-Lessons learned register, PM plan
updates, and org. process assets updates
QUESTION: Monitor and Control Project Work, Inputs - ANSWER-PM plan, proj. docs, work
performance information, agreements, enter. enviro. factors, and org. process assets
QUESTION: Monitor and Control Project Work, Tools and Techniques - ANSWER-Expert
judgement, data analysis, decision making, and meetings
2
,Page 3 of 114
QUESTION: Monitor and Control Project Work, Outputs - ANSWER-Work performance reports,
change requests, PM plan updates, and proj. docs updates
QUESTION: Perform Integrated Change Control, Inputs - ANSWER-PM plan, proj. docs, work
performance reports, change requests, enter. enviro. factors, and org. process assets
QUESTION: Perform Integrated Change Control, Tools & Techniques - ANSWER-Expert
judgement, change control tools, data analysis, decision making, and meetings
QUESTION: Perform Integrated Change Control, Outputs - ANSWER-Approved change requests,
PM plan updates, and proj. documents updates.
QUESTION: Close Project or Phase, Inputs - ANSWER-Project charter, PM plan, pro. docs,
accepted deliverables, business docs, agreements, procurement docs, and org. process assets
QUESTION: Close Project or Phase, Tools & Techniques - ANSWER-Expert Judgement
Analytical Techniques
Meetings
3
, Page 4 of 114
QUESTION: Close Project or Phase, Outputs - ANSWER-Project document updates, Final
product/service/result transition, Final report, OPA updates
QUESTION: Plan Scope Management, Inputs - ANSWER-Project Charter, Project Management
Plan, EEFs, OPAs
QUESTION: Plan Scope Management, Tools & Techniques (s) - ANSWER-Expert judgement, Data
analysis, Meetings (s)
QUESTION: Plan Scope Management, Outputs - ANSWER-Scope Management Plan
Requirements Management Plan
QUESTION: Collect Requirements, Inputs - ANSWER-Project Charter, Project Management Plan,
Project documents, Business documents, Agreements, EEFs, OPAs
QUESTION: Collect Requirements, Tool and Techniques - ANSWER-Expert judgement, data
gathering, data analysis, decision making, data representation, interpersonal & team skills,
context diagram, and prototypes
QUESTION: Collect Requirements, Outputs - ANSWER-Requirements documentation
Requirements traceability matrix