100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
Florida electrical business exam #7 Questions with Solutions $14.49   Add to cart

Exam (elaborations)

Florida electrical business exam #7 Questions with Solutions

 3 views  0 purchase
  • Course
  • Florida business and finance
  • Institution
  • Florida Business And Finance

Florida electrical business exam #7

Preview 2 out of 7  pages

  • September 23, 2024
  • 7
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • Florida business and finance
  • Florida business and finance
avatar-seller
julianah420
Florida electrical business exam #7

The right to repossess or replevy unused materials from a jobsite will not be effective if
someone, in good faith, purchased it after removal from the site of the improvement. -
answerTrue.

The contractor must within _____ days after the receipt of the property owner's request,
furnishish to property owner or the property owner's agent a list of the subcontractors
and suppliers who have a contract with the contractor as of the date the request is
received by the contractor. - answer10 days.

A property perfected lien may be discharged by an order of the circuit court of the _____
where the property is located. - answercounty

When any interested party files a complaint, the clerk will issue a summons to the lienor
to show cause within _____ days why his or her lien should not to be enforced by action
or vacated and canceled of record. - answer20 days

If a lienor fails to show cause why his or her lien should not be enforced or fails to start
such action before the return date of the summons, the court will immediately order
cancellation of the lien. - answerTrue

No lien provided by part 713.22 will continue for longer then ____ years after the claim
of lien has been recorded. - answer1 year

No lien provided by part 713.22 will continue for no longer then _______ years after the
recording of an amended claim of lien that shows a later date of final furnishing of labor,
services, or materials. - answer1 year

The lien of any lienor upon whom Notice of contest of Lien is served and who fails to
institute a suit to enforce his or her lien within ________ days after service of such
notice will be extinguished automatically. - answer60

The payment bond is required to ______ an owner under s. 713.23 must be furnished
by the contractor in at least the amount of the original contract price before commencing
the construction of the improvement under the direct contract. - answerexempt

A copy the payment bond must be attached to the Notice of Commencement when it is
_______. - answerrecorded

Anyone who willfully files a fraudulent lien as defined in 713.31 commits a felony of the
______ degree - answerthird

, When a construction project is "put out" for bid, the contractors are given the plans and
specifications for the project. If any deviations for these specifications occur, who will be
held responsible and may be required to correct them at their own expense? -
answerThe contractor

The ______ for a protect are interpreted as a legal document that specifically defines
the responsibilities of the owner and his representatives intended for the project and
what the contractors responsibilities are. - answerspecifications

The CSI-MASTERFORMAT divides the specifications into __________ specific
divisions to provide a standard reference and filing numbers for bidding and contract
forms. - answer50

Which of the following would appear as a heading in the index of the General Clauses
and Conditions sections of General Requirements? - answerAll of these ( General
Conditions, Notice to Bidders and Proposal)

_________ is the contractors price for performing the work as specified. - answerThe
proposal

"Contract Documents" "Insurance," "payments," and "Guarantee" are some typical items
that would be included under what heading in the General Clauses and Conditions
section? - answerGeneral Conditions

The square footage method of estimating is always recommended for lump-sum
contracts. - answerFalse

The typical _______ provides the necessary control devices for the accumulation of
estimates into the final bid. - answerEstimate summary sheet

What type of estimate is an accurate estimating method that consists of listing all
material and labor needed for an element of work or project - answerDetailed Survey

_________ estimates are used as a check to determine if sufficient materials are
available to construct or complete a project. - answerMaterial

Which of the following are types of labor estimates?
I. Preliminary manpower estimates
II. Detailed manpower estimates
III.Production manpower estimates - answerI and II only

The satisfactory completion of the work for the stand number of dollars in a lump-sum
contract remains the obligation of the contractor regardless of the troubles that may be
experienced in the course of construction activities. - answerTrue

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller julianah420. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $14.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

62890 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$14.49
  • (0)
  Add to cart