Term 1 of 107
If a building is constructed using green procedures or guidelines, how much less energy will
be required to operate it?
30-36%
50-60%
45-51%
19-24%
Term 2 of 107
Which of the following is done by the post-tensioning contractor prior to pouring concrete?
the site is cleared of all debris and vegetation before Work begins
the concrete is pre-mixed with additives to enhance strength
the contractor submits a final design plan to the project manager
the tendons are encased in high-density polyethylene sheathing with a PT coating
Term 3 of 107
What does a lien waiver release the owner from?
losing ownership of the property
paying too much for services or materials
gaining additional rights to the property
being responsible for all project delays
,Term 4 of 107
Which documents are primarily used by the contractor and architect to monitor quality?
contract addenda
construction drawings
as built drawings
submittals, shop drawings, and samples
Term 5 of 107
For a worker in a trench what is the maximum lateral distance from a means of egress?
10'
75'
15'
25'
Term 6 of 107
Which formula describes a balance sheet?
current liabilities
assets = liabilities + owner's equity
net income = revenues - expenses
assets = liabilities + stockholders' equity
Term 7 of 107
Where a roof meets a vertical wall which is the best method to follow?
installing a skylight directly against the wall without any barriers
using only caulk to seal the joint between the roof and wall
placing shingles directly on the wall without any additional materials
install metal flashing under the shingles and siding
,Term 8 of 107
Wallboard inspections must be made when?
before the joints are taped
after the building is ready for occupancy
a longer time is needed
they should be stored in a covered container
Term 9 of 107
A surveying benchmark is at 88.6 feet. There is a reference stake set 7.8 feet lower than the
benchmark. If a ditch is to be excavated to a depth of 8.75 feet below the reference stake and
20 feet from the reference stake, what is the finished elevation of the bottom of the ditch?
71.9 feet
72.05 feet
105 feet
77.5 feet
Term 10 of 107
What does the term retainage mean?
an advance payment made before work begins
a percentage of the progress payment withheld by the owner
the final payment made after project completion
the total amount paid to subcontractors
, Term 11 of 107
What method is based on the actual costs?
cost overruns
unit price
cost plus
unit price method
Term 12 of 107
What documents are required from the contractor before a final release of money?
guarantee of payment
consent of surety
affidavit of payment
labor agreement
Term 13 of 107
Which if the following would be an acceptable condition for a contractor to refuse to perform
work on a project and not be a breach of contract?
a contractor's personal preference to avoid the project
a delay in the delivery of materials unrelated to site conditions
a change in project management that the contractor disagrees with
a site condition that prohibits the subcontractor from the performing the work
Term 14 of 107
When unloading trusses what should a builder do?
stack them in a random order for easy access
leave the trusses on the delivery truck until needed
unload as close as possible to the building site
unload them in a nearby parking lot
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller selftest. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $9.00. You're not tied to anything after your purchase.