Prime Contractor - Answer The ______asummes the entire responsibility under the contract Sub Contractor - Answer The ______ asummes responsibility with respect to his portion of the work 6ft - Answer Safety Belts shall be a min of 1/2 inch nylon and not allow a fall greater than ____ ...

[Show more]

Preview 4 out of 36  pages

  • September 27, 2024
  • 36
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • NC Contractor
  • NC Contractor
avatar-seller
TestSolver9
NC Building Contractor License Prep
Exam Questions 100% Well Answered.
Prime Contractor - Answer The ______asummes the entire responsibility under the contract



Sub Contractor - Answer The ______ asummes responsibility with respect to his portion of the work



6ft - Answer Safety Belts shall be a min of 1/2 inch nylon and not allow a fall greater than ____



8ft - Answer Safety Nets must extend _____ beyond the end of work surface



25ft - Answer Safety Nets must be positioned no more than _____ below work surface



10ft - Answer Heaters must not be located within ______ft of tarps, canvas or similar coverings



10ft - Answer Material Storage : Materials shall not be stored within ____ ft of an exterior wall



7ft - Answer Materaial Storage : Brick stacks shall not be more than _____ft in height



6ft - Answer Material Storage : When masonry blocks are stacked higher than _____ ft the stack shall be
tapered back 1 half block per tier above the ____ft line



20ft - Answer Material Storage : Lumber Piles shall not exceed ______ft in height (mechanically)



16ft - Answer Material Storage - Lumber piles shall not exceed _____ in height (manually)



20ft - Answer A chute is required if waste material is dropped more than _____ft outside exterior walls
of building

,8 Inches - Answer How far do you Lap Durawire



Confined - Answer workers in _____ spaces must be provided a lifeline/safety belt



Catenary Scaffold - Answer means a suspension scaffold consisting of a platform supported by two
essentially horiztonal & parallel ropes attached to structural members of a building or other structure



Prescription Lenses - Answer employer ensures that employees who wear presc lenses while engaged in
operations needing eye protection



12ft - Answer Maximum height of a masonry pier used in a seismic zone is _____



Float (Ship) Scaffold - Answer means a suspension scaffold consisting of a braced platform resin on two
parallel bearers & hung from overhead supports by ropes of fixed length



Lack Of Maintenance - Answer The leading reason for erosion and sediment conrol plan failure is _____



Potable Water & Detergents - Answer To clean masory use _______



Wood Girders : Wood - Answer No Masonry shall be supported on ______ or other forms of _____
construction



Roof Diaphragms : 15 Inches - Answer _______ Shall be anchored to masonry walls with 1/2" diameter
bolts 6ft on center or equivalent. Bolt shall extend & be embedded at least _____ in the masonry



8 Inches - Answer Minimum thickness of a parapet wall



24 Inches - Answer Maximum spacing of light gauge studs



TRUE - Answer Mechanicla connections shall have the bars connection to develop in tension or
compression as least 125% of the yield strength of the bar

,No - Answer Is a hardhat required with a jack hammer?



42" Reflectorized Barrell or Drum - Answer What is preferred safety traffic marker?



A penetrometer - Answer What is used to measure soil bearing capactiy?



Lap durawire 8 inches - Answer Lap durawire 8 inches



3 times - Answer Unreinforced masonry parapet wall heights shall not exceed _____ their thickness



6 Inches - Answer Minimum thickness of a masonry bearing wall - One Story



8 inches - Answer Minimum thickness of a masonry bearing wall - More than One Story



4.5 Sq Ft - Answer There shall be at least one metal tile for each ______ of wall area



24 Inches - Answer Vertical Spacing on Metal Wall Tie



36 Inches - Answer Horiztonal Spacing on Metal Wall Tie



3500 PSI - Answer The minimum compressive strength for a carport slab in severe exposure zone is
_____



Shut Off - Answer hand held power tools (circular saw, chain saw & percussion tools) require a constant
pressure switch that will _____the power when pressure is released



30 PSI - Answer Compressed air shall not be used for cleaning purposes except where reduced to less
than _____ PSI

, Trained - Answer Only employees who have been ____ in the operation of the particular tool in use
shall be allow to operate powder actuated tools



Circular Saws - Answer All Portable, power driven _____ shall be equipped with guards above and
below the base plate or shoe



Upright - Answer Compressed gas cylinders shall be secured in an ______ position at all times



20 Ft - Answer Oxygen Cylinders and fuel cylinders must be stored a minimum of ____ and when in
inside _____ from combustible materials



Inspected - Answer All gas and oxygen hoses must be _____ at the beginning of each work shift



8 and 11 - Answer Unless otherwise required, mix grout to a consistency that has a slumb between
______



Gravel - Answer Sediment Basins must be built over _____



1 Acre or Larger - Answer An erosion and sedimentation control plan must be approved before land
distrubance begins on any site ______



Slopes - Answer Runoff must be diverted across the ______



Acid : Caustic Solutions - Answer Unless otherwise required, do not use ______ or _______



Near The Source - Answer Where is sediment most effectively controlled?



Permanent Ground Cover - Answer A ______ sufficient to control erosion must be installed within 30
working days or 120 calendar days whichever is less after the construction is complete

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller TestSolver9. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $10.39. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

77254 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$10.39
  • (0)
  Add to cart