Minimum Standard 1 - Correct Answer Stabilization
permanent or temporary soil stabilization shall be applied to denuded areas within seven days after final grade is reached on any portion of the site; temporary soil stabilization shall be applied within seven days to denuded areas that may not...
Erosion and Sediment Control With Correct
Answers
Minimum Standard 1 - Correct Answer Stabilization
permanent or temporary soil stabilization shall be applied to denuded areas within seven days after final
grade is reached on any portion of the site; temporary soil stabilization shall be applied within seven
days to denuded areas that may not be at final grade but will remain dormant for longer than 14 days;
permanent stabilization shall be applied to areas that are to be left dormant for more than one year
Site NOT at Final Grade - Correct Answer - stabilize in 14 days
- temporarily seed
- mulch
- permanently stabilize if dormant > 1 year
Site at Final Grade - Correct Answer - stabilize in 7 days (recommended immediately)
- permanently or temporarily seed and mulch
- mulch/matting/straw
Minimum Standard 2 - Correct Answer Stock Piles, Waste and Borrow Areas
during construction, soil stock piles and borrow areas shall be stabilized or protected with sediment
trapping measures
mulch prevents erosion by protecting the surface from raindrop impact and silt fence intercepts and
detains from disturbed areas
Minimum Standard 3 - Correct Answer Permanent Vegetation
,permanent vegetation cover shall be established on denuded areas not otherwise permanently
stabilized (permanent vegetation shall not be considered established until a ground cover is achieved
that is uniform, mature enough to survive, and will inhibit erosion *there is no % associated with this*)
reduce erosion and decrease sediment yield from disturbed area
this is the standard used to verify that a site is ready for release of bonds or surety
Minimum Standard 4 - Correct Answer First-Step Measures
Sediment basins and traps, perimeter dikes, sediment barriers and other measures intended to trap
sediment shall be constructed as a first step in any land-disturbing activity and shall be made functional
before upslope land disturbance takes place
a certain amount of initial land disturbance may be required to provide access for equipment to install
the perimeter controls, but site clearing and grading should be kept to a minimum until the perimeter
controls are in place
intercepts and detains small amounts of sediment from disturbed areas during construction operation to
prevent sediment from leaving the site and decrease velocity of sheet flows and low-to-moderate level
channel flow
Perimeter Controls - Correct Answer assures that sediment does not leave the perimeter of the land-
disturbing area once site clearing, grading, and construction commences
Minimum Standard 5 - Correct Answer Earthen Structure Stabilization
stabilization measures shall be applied to earthen structures such as dams, dikes, and diversions
immediately after installation
, reduce erosion and sedimentation and reduce damage from sediment and runoff to downstream or off-
site areas
Minimum Standard 6 - Correct Answer Traps and Basins
sediment traps and basins shall be designed and constructed based upon the total drainage area (not
just disturbed area) to be served by the trap or basin
Sediment Traps - Correct Answer minimum storage capacity shall be 134 cubic yards per acre of
drainage area and shall only control drainage areas less than 3 acres
*stone outlet = trap*
Sediment Basins - Correct Answer surface runoff from disturbed areas that is comprised of flow from
drainage areas greater than or equal to 3 acres shall be controlled by a basin; minimum storage capacity
of a sediment basin shall be 134 cubic yards per acre of drainage area; the outfall system shall, at a
minimum, maintain the structural integrity of the basin during a 25-year storm of 24-hour duration;
runoff coefficients used in runoff calculations shall correspond to a bare earth condition or those
conditions expected to exist while the sediment basin is utilized.
Sediment Trapping Devises - Correct Answer 1. place near the lowest drainage points of a project
2. install as a first-step measure [MS-4]
3. stabilize immediately [MS-5]
4. must include outlet protection for basins [MS-11]
Minimum Standard 7 - Correct Answer Cut and Fill Slopes
roughening the surface of the slope decreases runoff, lowers the velocity runoff, increases water
retention, and leads to better seed germination
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller Victoria108. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $11.49. You're not tied to anything after your purchase.